Induction Sealing Machine – IQ Protocol

Installation Qualification Protocol for Induction Sealing Machine

Document ID: IQ-IS-001

Version: 1.0

Date: 2023-10-01

Prepared by: Validation Team

Reviewed by: Quality Assurance

Approved by: Department Head

Objective

The objective of this Installation Qualification (IQ) protocol is to verify that the Induction Sealing Machine is installed correctly and operates according to the specified requirements defined in the User Requirement Specification (URS) Annex11.

Scope

This protocol applies to the Installation Qualification of the Induction Sealing Machine used in the Packaging/Primary area for sealing liners in Solid Dosage Form (OSD) products.

Responsibilities

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the IQ documentation.
  • Maintenance Team: Responsible for providing technical support during the installation process.

Prerequisites

  • Completion of the equipment installation by the vendor.
  • Availability of the necessary documentation (user manuals, installation manuals).
  • Training of personnel on equipment operation.

Equipment Description

The Induction Sealing Machine is designed to seal liners in containers using electromagnetic induction technology. It is critical for maintaining product integrity and preventing contamination.

Test Plan

Test ID Procedure Acceptance Evidence
IQ-01 Verify installation location and utilities (power, air, etc.). All utilities meet specifications. Photographic evidence and utility checklists.
IQ-02 Check equipment setup and alignment. Equipment is correctly aligned and secured. Alignment verification report.
IQ-03 Verify critical parameter settings (power conveyor speed, seal integrity). Settings match URS Annex11 specifications. Parameter settings log.
IQ-04 Perform a dry run of the machine. No errors or malfunctions detected. Dry run log and observations.
See also  Automated Visual Inspection (AVI) Machine – IQ Protocol

Detailed Test Cases

Test ID: IQ-01

Procedure: Verify installation location and utilities (power, air, etc.).

Acceptance: All utilities meet specifications.

Evidence: Photographic evidence and utility checklists.

Test ID: IQ-02

Procedure: Check equipment setup and alignment.

Acceptance: Equipment is correctly aligned and secured.

Evidence: Alignment verification report.

Test ID: IQ-03

Procedure: Verify critical parameter settings (power conveyor speed, seal integrity).

Acceptance: Settings match URS Annex11 specifications.

Evidence: Parameter settings log.

Test ID: IQ-04

Procedure: Perform a dry run of the machine.

Acceptance: No errors or malfunctions detected.

Evidence: Dry run log and observations.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A deviation report should be generated and approved by the Quality Assurance team.

Approvals

This protocol must be reviewed and approved by the Quality Assurance team and the Department Head prior to execution.