Parts Washer (GMP) – PQ Protocol

Document Title: Performance Qualification Protocol for Parts Washer

Document Number: PQ-OSD-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Performance Qualification Protocol for GMP Parts Washer

Meta Description: This document outlines the Performance Qualification protocol for the Parts Washer used in Solid Dosage Form production, ensuring compliance with GMP standards.

Tags: Equipment Validation, Performance Qualification, GMP, Parts Washer, Solid Dosage Form

Objective

The objective of this Performance Qualification (PQ) protocol is to verify that the Parts Washer operates consistently and effectively to wash equipment parts used in the production of solid dosage forms, ensuring compliance with Good Manufacturing Practices (GMP).

Scope

This protocol applies to the Parts Washer utilized in the Production/Cleaning area for washing equipment parts that directly impact product quality.

Responsibilities

  • Validation Team: Responsible for executing the PQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Production Personnel: Responsible for operating the Parts Washer according to established procedures.

Prerequisites

  • Completion of Installation Qualification (IQ) and Operational Qualification (OQ).
  • Availability of necessary equipment and materials.
  • Training of personnel on the operation of the Parts Washer.

Equipment Description

The Parts Washer is a GMP-compliant piece of equipment designed to wash and sanitize equipment parts used in the production of solid dosage forms. Key features include programmable wash cycles, adjustable wash temperatures, and pressure settings.

See also  Tablet Deduster – PQ Protocol

Test Plan

Test ID Procedure Acceptance Criteria Evidence
PQ-01 Verify wash temperature Temperature within specified range Temperature log
PQ-02 Verify wash time Time meets specified duration Time log
PQ-03 Verify wash pressure Pressure within specified range Pressure log
PQ-04 Verify detergent dosing Correct dosage as per protocol Dosing log
PQ-05 Verify PLC functionality PLC operates without errors PLC report

Detailed Test Cases

Test Case PQ-01: Verify Wash Temperature

Objective: Ensure the wash temperature is maintained within the specified range during operation.

Procedure: Monitor and record the temperature during a wash cycle.

Acceptance Criteria: Temperature must be within the range of [Insert Range].

Evidence Required: Temperature log from the wash cycle.

Test Case PQ-02: Verify Wash Time

Objective: Confirm that the wash time meets the specified duration.

Procedure: Start the wash cycle and record the time taken.

Acceptance Criteria: Wash time must meet the duration of [Insert Duration].

Evidence Required: Time log from the wash cycle.

Test Case PQ-03: Verify Wash Pressure

Objective: Ensure that the wash pressure is maintained within the specified range.

Procedure: Monitor and record pressure during a wash cycle.

Acceptance Criteria: Pressure must be within the range of [Insert Range].

Evidence Required: Pressure log from the wash cycle.

Test Case PQ-04: Verify Detergent Dosing

Objective: Confirm that the detergent dosing is accurate as per protocol.

Procedure: Measure the amount of detergent used during the wash cycle.

Acceptance Criteria: Detergent dosing must match [Insert Dosage].

Evidence Required: Dosing log from the wash cycle.

Test Case PQ-05: Verify PLC Functionality

Objective: Ensure that the PLC operates without errors during the wash cycle.

See also  Binder Solution Preparation Tank – Qualification Certificate Template

Procedure: Monitor PLC outputs and log any errors during operation.

Acceptance Criteria: No errors must be reported during the wash cycle.

Evidence Required: PLC report from the wash cycle.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A root cause analysis should be performed, and corrective actions must be implemented as necessary.

Approvals

Prepared By: [Insert Name]    Date: [Insert Date]

Reviewed By: [Insert Name]    Date: [Insert Date]

Approved By: [Insert Name]    Date: [Insert Date]

Data Integrity Checks

Practical data integrity checks must include:

  • Regular audits of temperature, time, pressure, and dosing logs.
  • Cross-verification of manual entries against automated logs.
  • Periodic review of PLC error logs for discrepancies.