Bin/IBC Washer – IQ Protocol

Document Control:

Protocol Number: IQ-OSD-001

Version: 1.0

Date: 2023-10-01

Prepared By: [Your Name]

Approved By: [Approver’s Name]

Installation Qualification Protocol for Bin/IBC Washer

Objective: To verify that the Bin/IBC Washer is installed correctly and operates according to specified requirements for the cleaning of IBC/bin contact parts in the production area.

Scope: This protocol applies to the Installation Qualification of the Bin/IBC Washer used in the Solid Dosage Form (OSD) production and cleaning area. It covers all aspects of the equipment necessary for compliance with regulatory standards.

Responsibilities:

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Engineering: Responsible for ensuring the equipment is installed according to specifications.

Prerequisites:

  • Completion of the equipment installation.
  • Availability of all necessary documentation, including User Requirements Specification (URS) and equipment manuals.
  • Training of personnel on the operation of the Bin/IBC Washer.

Equipment Description:

The Bin/IBC Washer is designed to wash Intermediate Bulk Containers (IBCs) and bins used in the production of solid dosage forms. It operates under controlled conditions to ensure the effective removal of contaminants and residues.

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of all components. All components must be installed as per manufacturer specifications. Installation checklist signed and dated.
IQ-02 Check power and utilities connections. All connections must be secure and functional. Utility connection log.
IQ-03 Perform calibration checks on critical parameters. Wash temperature, time, pressure, and detergent dosing must meet specifications. Calibration certificates.
IQ-04 Verify PLC functionality. PLC must operate without errors during testing. PLC test report.
See also  Vision System (Label/Code Verification) – Qualification Certificate Template

Detailed Test Cases:

  • Test Case IQ-01: Ensure all components are correctly installed and secured.
  • Test Case IQ-02: Validate that electrical and water connections are correct and operational.
  • Test Case IQ-03: Measure wash temperature, time, pressure, and detergent dosing; document results.
  • Test Case IQ-04: Test PLC for functionality and error-free operation.

Deviations: Any deviations from the acceptance criteria must be documented and investigated. A corrective action plan should be developed for any critical failures.

Approvals:

_________________________

Prepared By: [Your Name]

_________________________

Approved By: [Approver’s Name]

Data Integrity Checks:

  • Ensure that all data recorded during the IQ process is timestamped and signed by the responsible personnel.
  • Review logs for any discrepancies or anomalies in the data collected.