Objective
The objective of this Installation Qualification (IQ) protocol is to verify that the Stainless Steel Reactor (SSR) is installed correctly and operates according to specified requirements for API synthesis reactions.
Scope
This protocol applies to the Stainless Steel Reactor (SSR) used in the production area for API manufacturing through chemical synthesis and purification processes.
Responsibilities
The Validation Team is responsible for executing this protocol, while the Quality Assurance Team will review and approve the results.
Prerequisites
- Completion of equipment installation.
- Availability of required documentation (URS, specifications).
- Training of personnel on equipment operation.
Equipment Description
The Stainless Steel Reactor (SSR) is designed for API synthesis reactions, featuring capabilities for temperature control, pressure regulation, agitation, and PLC audit trail logging, ensuring compliance with critical validation parameters.
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| IQ-SSR-001 | Verify installation against design specifications. | All components must match the URS requirements. | Installation checklist and photographs. |
| IQ-SSR-002 | Check calibration of temperature, pressure, and agitation controls. | Calibration within specified tolerances. | Calibration certificates. |
| IQ-SSR-003 | Test PLC audit trail functionality. | Audit trails must accurately log all operations. | Audit trail printouts. |
Detailed Test Cases
Test Case: IQ-SSR-001
Objective: Verify installation against design specifications.
Procedure: Inspect all components against the installation checklist.
Acceptance Criteria: All components must match the URS requirements.
Evidence: Documented checklist and photographs of the installation.
Test Case: IQ-SSR-002
Objective: Check calibration of temperature, pressure, and agitation controls.
Procedure: Use calibrated instruments to verify settings.
Acceptance Criteria: Calibration within specified tolerances.
Evidence: Calibration certificates and logs.
Test Case: IQ-SSR-003
Objective: Test PLC audit trail functionality.
Procedure: Perform operations and review audit logs.
Acceptance Criteria: Audit trails must accurately log all operations.
Evidence: Printed audit trail logs.
Deviations
Any deviations from the acceptance criteria must be documented and assessed for impact on validation status.