Homogenizer (Inline / High Shear) – DQ Protocol

Document Control

Document Number: DQ-001

Version: 1.0

Effective Date: 2023-10-01

Reviewed By: [Name]

Approval Date: [Date]

Design Qualification Protocol for Inline/High Shear Homogenizer

Objective

The objective of this Design Qualification (DQ) protocol is to ensure that the Inline/High Shear Homogenizer is designed and installed in accordance with the specified requirements to ensure uniform API dispersion in the production of suppositories and implants.

Scope

This protocol applies to the validation of Inline/High Shear Homogenizers used in the production area for the manufacturing of suppositories and implants. It encompasses equipment qualification, operational parameters, and data integrity checks.

Responsibilities

The Validation Team is responsible for executing this protocol. Quality Assurance will oversee the approval process, while Production will provide operational support and access to the equipment.

Prerequisites

  • Completion of User Requirement Specification (URS).
  • Installation Qualification (IQ) of the equipment.
  • Availability of necessary documentation (SOPs, maintenance logs).

Equipment Description

The Inline/High Shear Homogenizer is designed to achieve uniform dispersion of active pharmaceutical ingredients (APIs) in the formulation of suppositories and implants. Key features include adjustable speed settings, temperature control, and integrated PLC for data logging.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
DQ-01 Verify speed settings Speed within specified range as per URS Calibration logs
DQ-02 Check temperature control Temperature maintained within specified limits Temperature logs
DQ-03 Assess shear force Shear force meets defined specifications Shear force logs
DQ-04 Review PLC logs Logs show complete audit trail PLC audit trail report

Detailed Test Cases

Test Case DQ-01: Verify Speed Settings

Procedure: Adjust the speed settings on the homogenizer and record the actual speeds. Compare with the specified range in the URS.

See also  Tablet Compression Machine (Single Rotary) – Equipment Validation SOP

Acceptance Criteria: Speed must be within the specified range.

Evidence: Calibration logs must be documented and reviewed.

Test Case DQ-02: Check Temperature Control

Procedure: Operate the homogenizer and monitor temperature throughout the process.

Acceptance Criteria: Temperature must remain within specified limits.

Evidence: Temperature logs must be maintained for review.

Test Case DQ-03: Assess Shear Force

Procedure: Measure the shear force during operation using calibrated equipment.

Acceptance Criteria: Shear force must meet defined specifications.

Evidence: Shear force logs must be documented.

Test Case DQ-04: Review PLC Logs

Procedure: Access PLC logs and verify the completeness of the audit trail.

Acceptance Criteria: Logs must show a complete audit trail without discrepancies.

Evidence: PLC audit trail report must be available for review.

Deviations

Any deviations from the acceptance criteria must be documented and addressed through a formal change control process. Investigations must be conducted to determine the root cause and corrective actions implemented.

Approvals

All results must be reviewed and approved by the Validation Manager and Quality Assurance prior to final acceptance of the equipment for use in production.