Blow-Fill-Seal (BFS) Machine – OQ Protocol

Operational Qualification Protocol for Blow-Fill-Seal Machine in IV Infusions

Document Number: OQ-BFS-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Objective

The objective of this Operational Qualification (OQ) protocol is to verify that the Blow-Fill-Seal (BFS) Machine operates within specified limits and meets the requirements outlined in the User Requirement Specification (URS) and applicable guidelines.

Scope

This protocol applies to the Blow-Fill-Seal Machine used in the production of IV Infusions (LVP/SVP – Bags/Bottles) within the Production area. It covers the operational parameters critical to the equipment’s performance.

Responsibilities

  • Validation Team: Responsible for executing the OQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Production Personnel: Responsible for operating the equipment during the qualification process.

Prerequisites

Ensure that the Blow-Fill-Seal Machine is installed, calibrated, and maintained according to the manufacturer’s specifications. Relevant training must be completed by all personnel involved.

Equipment Description

The Blow-Fill-Seal (BFS) Machine is designed to blow containers and aseptically fill them with IV solutions. It operates under controlled conditions to ensure sterility and product integrity.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
OQ-001 Verify mold temperature settings. Mold temperature within specified range. Temperature log.
OQ-002 Check fill accuracy. Fill volume within ±5% of target. Weighing results.
OQ-003 Test sterile zone airflow alarms. Alarms activate within specified limits. Alarm log.
OQ-004 Review audit trail functionality. Audit trail reflects all critical actions. Audit trail report.
See also  Bin Lifter / IBC Lifter – Qualification Execution Checklist

Detailed Test Cases

Test Case OQ-001: Mold Temperature Verification

Procedure: Set the mold temperature to the specified setting and monitor for stability.

Acceptance Criteria: The mold temperature must remain within the defined range throughout the test period.

Evidence: Document temperature readings and stability observations in the log.

Test Case OQ-002: Fill Accuracy Check

Procedure: Fill a series of containers and measure the fill volume.

Acceptance Criteria: The average fill volume must be within ±5% of the target volume.

Evidence: Record measurements and calculate averages for review.

Test Case OQ-003: Airflow Alarm Testing

Procedure: Simulate airflow disruptions and observe alarm activation.

Acceptance Criteria: Alarms must activate within specified parameters.

Evidence: Document alarm responses and any deviations.

Test Case OQ-004: Audit Trail Review

Procedure: Access the audit trail and verify the recording of critical actions.

Acceptance Criteria: All critical actions must be documented with timestamps.

Evidence: Print or export audit trail for review.

Deviations

Any deviations from the acceptance criteria must be documented, including the reason for the deviation and any corrective actions taken.

Approvals

Prepared By: ______________________ Date: __________

Approved By: ______________________ Date: __________