Objective

The objective of this Installation Qualification (IQ) protocol is to ensure that the Drying Oven used for the drying of solvent from coated patch film meets predefined specifications and is installed correctly for the production of Transdermal Patches.

Scope

This protocol applies to the Drying Oven utilized in the Production area for the direct impact on the Transdermal Patches (TDS) manufacturing process.

Responsibilities

  • Validation Team: Responsible for the execution and documentation of the IQ protocol.
  • Engineering Team: Responsible for the installation and maintenance of the Drying Oven.
  • Quality Assurance: Responsible for the review and approval of the IQ protocol and results.

Prerequisites

  • Completion of equipment installation by the Engineering Team.
  • Availability of relevant documentation, including User Requirement Specifications (URS) and equipment manuals.
  • Training of personnel on equipment operation and safety procedures.

Equipment Description

The Drying Oven is designed to remove solvents from coated patch films efficiently. It operates under controlled temperature and airflow conditions to ensure optimal drying times and solvent removal.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation against manufacturer specifications. All components installed as per specifications. Installation checklist and photographs.
IQ-02 Check calibration of temperature and airflow sensors. Calibration within specified limits. Calibration certificates.
IQ-03 Perform drying time tests with solvent-coated patches. Solvent removal meets specified drying time. Test results and logs.
IQ-04 Review PLC logs for operational consistency. Logs indicate normal operational parameters. PLC log reports.
See also  Filter Housing (Sterile Grade) – Qualification Execution Checklist

Detailed Test Cases

Test Case IQ-01

Objective: Verify installation against manufacturer specifications.

Procedure: Inspect all components and compare with the installation checklist provided by the manufacturer.

Acceptance Criteria: All components installed as per specifications.

Evidence: Installation checklist and photographs.

Test Case IQ-02

Objective: Check calibration of temperature and airflow sensors.

Procedure: Use calibration equipment to verify that sensors are within specified limits.

Acceptance Criteria: Calibration within specified limits.

Evidence: Calibration certificates.

Test Case IQ-03

Objective: Perform drying time tests with solvent-coated patches.

Procedure: Run the drying oven with solvent-coated patches and measure the time taken for solvent removal.

Acceptance Criteria: Solvent removal meets specified drying time.

Evidence: Test results and logs.

Test Case IQ-04

Objective: Review PLC logs for operational consistency.

Procedure: Analyze PLC logs for any anomalies during operation.

Acceptance Criteria: Logs indicate normal operational parameters.

Evidence: PLC log reports.

Deviations

Any deviations from the acceptance criteria must be documented and addressed in accordance with the Change Control procedure.

Approvals

Approved By: [Approver Name]