Crystallizer – Traceability Matrix (URS ↔ Tests)

URS ID URS Statement Risk (H/M/L) DQ Test Ref IQ Test Ref OQ Test Ref PQ Test Ref Evidence/Record Result
URS-001 The crystallizer must maintain a specified temperature during the crystallization process. H DQ-001 IQ-001 OQ-001 PQ-001 Temperature logs [Result]
URS-002 The cooling rate must be controlled to ensure optimal crystallization. M DQ-002 IQ-002 OQ-002 PQ-002 Cooling rate records [Result]
URS-003 Agitation must be maintained at specified levels to ensure uniformity. H DQ-003 IQ-003 OQ-003 PQ-003 Agitation logs [Result]
URS-004 The PLC must provide an audit trail for all operations. H DQ-004 IQ-004 OQ-004 PQ-004 PLC audit trail logs [Result]