Desiccant Inserter (if required) – PQ Protocol

Performance Qualification Protocol for Desiccant Inserter in Transdermal Patch Production

Document Control Number: PQ-TDS-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Objective

The objective of this Performance Qualification (PQ) protocol is to ensure that the Desiccant Inserter operates according to predefined specifications and meets the acceptance criteria outlined in the User Requirement Specification (URS) Annex 11 for the insertion of desiccants into pouches and cartons for transdermal patches.

Scope

This protocol applies to the validation of the Desiccant Inserter used in the packaging area for the insertion of desiccants into pouches/cartons for transdermal patches. The impact on product quality is indirect, and the criticality of this process is classified as major.

Responsibilities

The Validation Team is responsible for executing the PQ protocol, while the Quality Assurance (QA) department will review and approve the documentation. The Equipment Owner is responsible for ensuring the equipment is maintained and calibrated prior to testing.

Prerequisites

1. Equipment must be installed and calibrated according to the manufacturer’s specifications.

2. Operators must be trained on the use of the Desiccant Inserter.

3. All necessary materials and documentation must be available prior to testing.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
PQ-TDS-01 Verify placement accuracy of desiccants. Placement accuracy within ±1mm. Measurement logs and photographs.
PQ-TDS-02 Check reject logic functionality. 100% rejection of incorrect placements. System logs and reports.
PQ-TDS-03 Audit trail verification. Complete and accurate audit trail for each batch. Audit trail report.

Detailed Test Cases

Test Case: PQ-TDS-01

Objective: To verify the placement accuracy of desiccants.

Methodology: Measure the placement of desiccants in 10 samples and record the measurements.

Expected Outcome: All measurements should fall within ±1mm of the target placement.

Test Case: PQ-TDS-02

Objective: To evaluate the functionality of reject logic.

Methodology: Simulate incorrect placements and verify that the system rejects them.

Expected Outcome: The system should reject all incorrectly placed desiccants.

Test Case: PQ-TDS-03

Objective: To confirm the integrity of the audit trail.

Methodology: Generate an audit trail report for a completed batch and review for completeness.

Expected Outcome: The audit trail should be complete and accurately reflect all actions taken during the batch.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. The validation team will determine the impact of these deviations on product quality and compliance.

Approvals

Prepared by: ____________________ Date: __________

Reviewed by: ____________________ Date: __________

Approved by: ____________________ Date: __________