Purpose
The purpose of this SOP is to establish a standardized procedure for the validation of the Extrusion Machine utilized in the production of drug-eluting and biodegradable implants, ensuring compliance with regulatory requirements and product quality standards.
Scope
This procedure applies to the validation of the Extrusion Machine located in the Production area, specifically for the extrusion of implant materials. It encompasses all phases of validation including Design Qualification (DQ), Installation Qualification (IQ), Operational Qualification (OQ), and Performance Qualification (PQ).
Definitions
- Extrusion Machine: Equipment used to shape and form implant materials through the extrusion process.
- Validation: The documented evidence that a process, system, or equipment consistently produces a result meeting predetermined specifications.
- Criticality: The level of impact on product quality; in this case, classified as critical.
- CSV: Computerized System Validation.
Roles
- Validation Team: Responsible for planning, executing, and documenting the validation process.
- Quality Assurance: Ensures compliance with regulatory standards and reviews validation documentation.
- Production Personnel: Operate the Extrusion Machine and provide input during the validation process.
Lifecycle Procedure
- Design Qualification (DQ): Define user requirements and specifications.
- Installation Qualification (IQ): Verify that the equipment is installed correctly and meets specifications.
- Operational Qualification (OQ): Confirm that the equipment operates according to its intended use under normal operating conditions.
- Performance Qualification (PQ): Demonstrate that the equipment consistently performs as required during actual production runs.
Good Documentation Practices (GDP) Controls
All validation activities must be documented in accordance with Good Documentation Practices to ensure traceability and compliance with regulatory requirements. Documentation should include all validation protocols, reports, and deviations.
Acceptance Criteria Governance
Acceptance criteria must be established based on User Requirements Specification (URS) and Annex 11 compliance. All criteria must be met during the validation process to ensure equipment reliability and product quality.
Calibration and Preventive Maintenance (PM) Governance
The Extrusion Machine must undergo regular calibration and preventive maintenance as per the manufacturer’s recommendations and internal procedures to ensure optimal performance and compliance.
Change Control Triggers
Any changes to the Extrusion Machine or its operating procedures must be assessed for impact on validation status and require a formal change control process.
Revalidation Triggers and Periodic Review
Revalidation of the Extrusion Machine is required every 12 months or when significant changes occur that may impact its performance or product quality.
Records and Attachments
- Validation Protocols
- Validation Reports
- Calibration Records
- Preventive Maintenance Logs
- Change Control Documentation