Standard Operating Procedure for Equipment Validation of Inline Checkweigher in Ophthalmics
Purpose: This SOP outlines the validation process for the Inline Checkweigher used in the packaging of sterile eye drops and ointments to ensure compliance with regulatory requirements and product quality.
Scope: This procedure applies to the validation of the Inline Checkweigher within the Packaging/Primary area for ophthalmic products.
Definitions:
- Equipment Validation: The process of ensuring that the equipment operates according to its intended use and meets specified requirements.
- Criticality: The importance of the equipment in maintaining product quality; classified as Critical for the Inline Checkweigher.
- DQ/IQ/OQ/PQ: Design Qualification, Installation Qualification, Operational Qualification, Performance Qualification.
Roles:
- Validation Team: Responsible for the execution of validation activities.
- Quality Assurance: Ensures compliance with regulatory standards and reviews validation documentation.
- Maintenance Team: Conducts calibration and preventive maintenance as per schedule.
Lifecycle Procedure:
- Design Qualification (DQ): Document user requirements and specifications.
- Installation Qualification (IQ): Verify installation and documentation compliance.
- Operational Qualification (OQ): Test operational parameters and functionality.
- Performance Qualification (PQ): Validate equipment performance under actual operating conditions.
GDP Controls: Good Documentation Practices must be followed throughout the validation process, ensuring all records are complete, accurate, and legible.
Acceptance Criteria Governance: Acceptance criteria will be governed by the User Requirements Specification (URS) as per Annex 11 compliance.
Calibration/PM Governance: The Inline Checkweigher will undergo calibration and preventive maintenance every 12 months, with records maintained as per company policy.
Change Control Triggers: Any changes in equipment, processes, or materials that may impact the validation status will trigger a change control process.
Revalidation Triggers and Periodic Review: Revalidation will occur every 12 months or upon significant changes to the equipment or process.
Records/Attachments List:
- Validation Protocols
- Calibration Certificates
- Change Control Records
- Periodic Review Reports
- Training Records