Vision System (Code/Label Verification) – IQ Protocol

Document Control

Document Number: IQ-001

Version: 1.0

Effective Date: YYYY-MM-DD

Reviewed By: [Reviewer Name]

Approved By: [Approver Name]

Installation Qualification Protocol for Vision System in IV Infusions

Meta Description: This document outlines the Installation Qualification (IQ) protocol for the Vision System used in IV Infusions, ensuring compliance with regulatory standards and operational efficiency.

Tags: Equipment Validation, IV Infusions, Vision System, Quality Assurance

Objective

The objective of this Installation Qualification (IQ) protocol is to verify that the Vision System for code and label verification is installed correctly and operates as intended in the packaging and inspection area, ensuring compliance with the User Requirement Specification (URS) Annex 11.

Scope

This protocol applies to the Vision System utilized in the verification of labels and codes for IV Infusions (LVP/SVP – Bags/Bottles) within the packaging area. It encompasses installation verification, functionality checks, and performance metrics.

Responsibilities

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Engineering: Responsible for ensuring the system is installed according to specifications.

Prerequisites

  • Completion of equipment installation.
  • Availability of operational manuals and specifications.
  • Training of personnel on the Vision System.

Equipment Description

The Vision System is designed to verify labels and codes on IV Infusions (LVP/SVP – Bags/Bottles). It features capabilities for high-read rate, reject logic, and audit trail functionalities to ensure compliance and traceability.

See also  Inline Sifter (Transfer Line) – Qualification Certificate Template

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of Vision System components. All components installed as per specifications. Installation checklist.
IQ-02 Perform functionality test on read rate. Read rate ≥ 99%. Test report.
IQ-03 Audit trail verification. Audit trail logs are complete and accessible. Audit log review.
IQ-04 Reject logic test. Reject logic functions correctly as per specifications. Test results.

Detailed Test Cases

Test Case IQ-01: Installation Verification

Procedure: Check that all components of the Vision System are installed according to the manufacturer’s specifications.

Acceptance Criteria: All components must match the installation checklist without discrepancies.

Evidence: Completed installation checklist signed off by the validation team.

Test Case IQ-02: Read Rate Functionality

Procedure: Conduct tests using a variety of labels and codes to ensure the system achieves the required read rate.

Acceptance Criteria: The system must demonstrate a read rate of 99% or higher across all test samples.

Evidence: Documented test results showing read rates for each sample.

Test Case IQ-03: Audit Trail Verification

Procedure: Review the audit trail generated by the system to ensure all actions are logged correctly.

Acceptance Criteria: The audit trail must show complete records of all operations performed by the Vision System.

Evidence: Printed audit log for review.

Test Case IQ-04: Reject Logic Functionality

Procedure: Test the system’s reject logic by inputting both valid and invalid codes.

Acceptance Criteria: The system must reject invalid codes and accept valid ones without error.

Evidence: Test results documenting the outcomes of each input.

Deviations

Any deviations observed during the execution of this protocol will be documented and assessed. A deviation report will be generated if acceptance criteria are not met, detailing the nature of the deviation and corrective actions taken.

See also  Vent Filter Assembly – Qualification Certificate Template

Approvals

Prepared By: ________________________ Date: _______________

Reviewed By: ________________________ Date: _______________

Approved By: ________________________ Date: _______________