Objective
The objective of this Performance Qualification (PQ) protocol is to demonstrate that the Spray Dryer operates consistently within defined parameters to produce engineered inhalation particles meeting product specifications.
Scope
This protocol applies to the Spray Dryer utilized in the R&D and Production areas for the manufacture of inhaled NDDS powders. It encompasses all critical parameters affecting product quality.
Responsibilities
- Validation Team: Responsible for executing the PQ protocol and documenting results.
- Quality Assurance: Ensures compliance with regulatory requirements and reviews documentation.
- Production Team: Operates the equipment as per the protocol and assists in data collection.
Prerequisites
- Completion of Installation Qualification (IQ) and Operational Qualification (OQ) for the Spray Dryer.
- Availability of necessary materials and resources for testing.
- Training of personnel on equipment operation and data collection procedures.
Equipment Description
The Spray Dryer is designed to produce respirable particles through controlled atomization of a liquid feed. Key features include adjustable inlet and outlet temperatures, atomization airflow control, and a comprehensive solvent handling system.
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| PQ-001 | Measure inlet and outlet temperatures during operation. | Inlet temp: [X]°C, Outlet temp: [Y]°C | Temperature logs |
| PQ-002 | Verify atomization airflow settings. | Airflow: [Z] L/min | Airflow meter readings |
| PQ-003 | Assess solvent handling procedures. | Solvent purity: [Criteria] | Solvent analysis report |
| PQ-004 | Audit trail verification for data integrity. | Complete audit trail with no discrepancies. | Audit trail report |
Detailed Test Cases
Test Case 1: Inlet/Outlet Temperature Measurement
Procedure: Operate the Spray Dryer under standard conditions and record inlet and outlet temperatures at specified intervals.
Acceptance Criteria: Inlet temperature must remain within [X]°C and outlet temperature within [Y]°C.
Evidence: Temperature logs must be documented and signed by the operator.
Test Case 2: Atomization Airflow Verification
Procedure: Adjust the airflow settings and measure with an airflow meter.
Acceptance Criteria: Airflow must be maintained at [Z] L/min.
Evidence: Airflow meter readings must be recorded and signed off.
Test Case 3: Solvent Handling Assessment
Procedure: Review solvent handling procedures and perform purity tests.
Acceptance Criteria: Solvent purity must meet [Criteria].
Evidence: Solvent analysis report must be attached.
Test Case 4: Audit Trail Verification
Procedure: Review the electronic records for completeness and accuracy.
Acceptance Criteria: No discrepancies found in the audit trail.
Evidence: Audit trail report must be included in documentation.
Deviations
Any deviations from the acceptance criteria must be documented with justifications and approved by the Quality Assurance team.
Approvals
Prepared By: [Name] – [Title] – Date: [Date]
Reviewed By: [Name] – [Title] – Date: [Date]
Approved By: [Name] – [Title] – Date: [Date]