Document Control
Document ID: IQ-PW-001
Version: 1.0
Effective Date: 2023-10-01
Review Date: 2024-10-01
Prepared by: [Your Name]
Approved by: [Approver’s Name]
Installation Qualification Protocol for Purified Water Generation System
Meta Description: This document outlines the Installation Qualification (IQ) Protocol for the Purified Water Generation System (PW System) used in utilities for generating purified water, ensuring compliance with URS Annex 11 and Annex 15.
Tags: Equipment Validation, Utilities, Purified Water System, IQ Protocol
Objective
The objective of this Installation Qualification (IQ) Protocol is to verify that the Purified Water Generation System (PW System) is installed according to the manufacturer’s specifications and is capable of performing its intended function in compliance with regulatory requirements.
Scope
This protocol applies to the Installation Qualification of the Purified Water Generation System (PW System) located in the Utilities area and is intended for generating purified water that has a direct impact on the product.
Responsibilities
- Validation Team: Responsible for executing the IQ protocol and documenting results.
- Quality Assurance: Responsible for reviewing and approving the IQ protocol and results.
- Maintenance Team: Responsible for ensuring the system is properly installed and maintained.
Prerequisites
- Installation of the Purified Water Generation System must be completed.
- All necessary utilities (water, electricity) must be available.
- Personnel must be trained on the equipment and validation processes.
Equipment Description
The Purified Water Generation System (PW System) is designed to produce purified water through various processes ensuring compliance with industry standards. Key features include:
- Conductivity monitoring
- Total Organic Carbon (TOC) measurement
- Flow rate control
- Temperature regulation
- Pressure monitoring
- Audit trail capabilities
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| IQ-01 | Verify installation according to manufacturer’s specifications. | All components installed as per specifications. | Installation checklist signed off. |
| IQ-02 | Conductivity test at output. | Conductivity < 1.3 µS/cm. | Conductivity test results report. |
| IQ-03 | TOC measurement. | TOC < 500 ppb. | TOC measurement report. |
| IQ-04 | Flow rate verification. | Flow rate within specified range. | Flow rate verification log. |
| IQ-05 | Temperature check. | Temperature within specified limits. | Temperature log. |
| IQ-06 | Pressure check. | Pressure within specified limits. | Pressure log. |
| IQ-07 | Audit trail verification. | Audit trail functional and complete. | Audit trail report. |
Detailed Test Cases
Test Case IQ-01
Objective: Verify installation according to manufacturer’s specifications.
Procedure: Inspect all components and compare with installation manual.
Acceptance Criteria: All components installed as per specifications.
Evidence: Installation checklist signed off.
Test Case IQ-02
Objective: Conductivity test at output.
Procedure: Measure output conductivity using calibrated equipment.
Acceptance Criteria: Conductivity < 1.3 µS/cm.
Evidence: Conductivity test results report.
Test Case IQ-03
Objective: TOC measurement.
Procedure: Measure TOC using validated method.
Acceptance Criteria: TOC < 500 ppb.
Evidence: TOC measurement report.
Test Case IQ-04
Objective: Flow rate verification.
Procedure: Measure flow rate at specified points.
Acceptance Criteria: Flow rate within specified range.
Evidence: Flow rate verification log.
Test Case IQ-05
Objective: Temperature check.
Procedure: Measure temperature at output.
Acceptance Criteria: Temperature within specified limits.
Evidence: Temperature log.
Test Case IQ-06
Objective: Pressure check.
Procedure: Measure pressure at designated points.
Acceptance Criteria: Pressure within specified limits.
Evidence: Pressure log.
Test Case IQ-07
Objective: Audit trail verification.
Procedure: Review audit trail for completeness and functionality.
Acceptance Criteria: Audit trail functional and complete.
Evidence: Audit trail report.
Deviations
Any deviations from the acceptance criteria must be documented and investigated. A deviation report should be generated and submitted to Quality Assurance for review.
Approvals
Document prepared by: ___________________________ Date: ____________
Approved by: ___________________________ Date: ____________