AHU for Aseptic Area – IQ Protocol

Document Control

Document Number: IQ-AHU-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Installation Qualification Protocol for AHU in Aseptic Area

Meta Description: This document outlines the Installation Qualification (IQ) protocol for the Air Handling Unit (AHU) serving the aseptic area, ensuring compliance with critical parameters for sterile injectables.

Objective

The objective of this Installation Qualification (IQ) protocol is to verify that the Air Handling Unit (AHU) for the aseptic area is installed correctly and operates within specified limits to ensure compliance with regulatory requirements for sterile injectables.

Scope

This protocol applies to the Air Handling Unit (AHU) utilized in the aseptic area of the Engineering department, specifically for HVAC serving classified rooms impacting product quality.

Responsibilities

The Validation Team is responsible for executing this protocol, documenting results, and addressing deviations. Engineering will oversee installation and maintenance of the AHU.

Prerequisites

All installation activities must be completed, and necessary documentation (e.g., URS, design specifications) must be available for review prior to executing this protocol.

Equipment Description

The AHU is designed to provide controlled airflow, temperature, and humidity for classified aseptic areas, ensuring compliance with critical parameters such as ACH, airflow, temperature, relative humidity, differential pressure, alarms, trends, and audit trails.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-001 Verify installation of AHU components All components installed as per specifications Installation checklist
IQ-002 Check ACH airflow ACH within specified limits Flow measurement data
IQ-003 Measure temperature and RH Temperature and RH within specified limits Calibration certificates
IQ-004 Verify differential pressure DP within specified limits Pressure measurement data
IQ-005 Test alarm functionality All alarms functional and documented Alarm test report
IQ-006 Review trends and audit trails All records complete and accurate Audit trail review documentation
See also  Octagonal Blender – Qualification Execution Checklist

Detailed Test Cases

Test ID IQ-001: Verify installation of AHU components.

Procedure: Inspect all components against installation checklist.

Acceptance Criteria: All components must match specifications.

Evidence: Complete installation checklist with signatures.

Test ID IQ-002: Check ACH airflow.

Procedure: Measure airflow using an anemometer.

Acceptance Criteria: ACH must be within specified limits.

Evidence: Flow measurement data report.

Test ID IQ-003: Measure temperature and RH.

Procedure: Use calibrated sensors to measure temperature and RH.

Acceptance Criteria: Both parameters must be within specified limits.

Evidence: Calibration certificates and measurement logs.

Test ID IQ-004: Verify differential pressure.

Procedure: Measure DP across HEPA filters.

Acceptance Criteria: DP must fall within specified limits.

Evidence: Pressure measurement data report.

Test ID IQ-005: Test alarm functionality.

Procedure: Trigger alarms and verify response.

Acceptance Criteria: All alarms must activate as expected.

Evidence: Alarm test report with timestamps.

Test ID IQ-006: Review trends and audit trails.

Procedure: Examine historical data and audit trails for completeness.

Acceptance Criteria: All records must be accurate and up-to-date.

Evidence: Audit trail review documentation.

Deviations

Any deviations from the acceptance criteria must be documented, investigated, and resolved prior to final approval of the IQ protocol.

Approvals

Prepared By: [Insert Name]

Approved By: [Insert Name]

Date: [Insert Date]