Water for Injection System (WFI Generation) – IQ Protocol

Document Control

Document Number: IQ-WFI-001

Version: 1.0

Effective Date: [Insert Date]

Prepared by: [Insert Name]

Approved by: [Insert Name]

Installation Qualification Protocol for Water for Injection System

Meta Description: This document outlines the Installation Qualification (IQ) Protocol for the Water for Injection (WFI) System, ensuring compliance with critical parameters and acceptance criteria.

Objective

The objective of this Installation Qualification (IQ) Protocol is to verify that the Water for Injection (WFI) System is installed according to the design specifications and operational requirements, ensuring it meets the necessary standards for generating WFI.

Scope

This protocol applies to the Installation Qualification of the Water for Injection (WFI) System located in the Utilities area. It covers all aspects of installation, including equipment setup, configuration, and initial performance verification.

Responsibilities

Validation Team: Responsible for executing the IQ protocol and documenting results.

Quality Assurance: Responsible for reviewing and approving the IQ protocol and results.

Maintenance Team: Responsible for ensuring the equipment is maintained and operational prior to IQ execution.

Prerequisites

All installation activities must be completed, and the system should be ready for qualification. Relevant documentation, including User Requirements Specifications (URS), should be reviewed prior to the initiation of the IQ protocol.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-001 Verify installation against design specifications All components installed as per specifications Installation checklist
IQ-002 Check functionality of conductivity meter Conductivity < 1.3 µS/cm Calibration certificate
IQ-003 Verify TOC levels TOC < 500 ppb TOC measurement report
IQ-004 Microbial testing No microbial growth detected Microbial test results
IQ-005 Temperature verification Temperature maintained at 20-25°C Temperature log
IQ-006 Audit trail verification Audit trail functionality confirmed Audit trail report

Detailed Test Cases

Test ID: IQ-001

Procedure: Confirm all installation points are completed as per the design specifications.

Acceptance Criteria: All components must be installed correctly.

Evidence: Installation checklist signed off by the validation team.

Test ID: IQ-002

Procedure: Test the conductivity meter with a known standard.

Acceptance Criteria: Conductivity reading must be less than 1.3 µS/cm.

Evidence: Calibration certificate showing the meter is within specification.

Test ID: IQ-003

Procedure: Measure TOC levels using the designated TOC analyzer.

Acceptance Criteria: TOC levels must be below 500 ppb.

Evidence: TOC measurement report from the analyzer.

Test ID: IQ-004

Procedure: Conduct microbial testing on the output water.

Acceptance Criteria: No microbial growth should be detected.

Evidence: Microbial test results report.

Test ID: IQ-005

Procedure: Monitor and record the temperature of the system.

Acceptance Criteria: Temperature must be maintained between 20-25°C.

Evidence: Temperature log documenting the readings.

Test ID: IQ-006

Procedure: Verify that the audit trail is functioning correctly.

Acceptance Criteria: Audit trail must document all system interactions.

Evidence: Audit trail report confirming functionality.

Approvals

All results must be reviewed and approved by the Quality Assurance team before the Water for Injection System is deemed qualified for use.