Vacuum Emulsifier (Main Manufacturing Vessel) – Traceability Matrix (URS ↔ Tests)

URS ID URS Statement Risk (H/M/L) DQ Test Ref IQ Test Ref OQ Test Ref PQ Test Ref Evidence/Record Result
URS-001 Ensure the emulsifier achieves the required agitation speed. M DQ-001 IQ-001 OQ-001 PQ-001 Agitation Speed Log Pass
URS-002 Verify the temperature control during emulsification. M DQ-002 IQ-002 OQ-002 PQ-002 Temperature Log Pass
URS-003 Confirm vacuum level is maintained throughout the process. H DQ-003 IQ-003 OQ-003 PQ-003 Vacuum Log Pass
URS-004 Ensure proper homogenization is achieved. M DQ-004 IQ-004 OQ-004 PQ-004 Homogenization Report Pass
URS-005 Verify PLC logs are accurately recorded. L DQ-005 IQ-005 OQ-005 PQ-005 PLC Log Review Pass