Installation Qualification Protocol for HEPA Integrity Test System

This document outlines the Installation Qualification (IQ) protocol for the HEPA Integrity Test System used in sterile (injectables/aseptic) environments to ensure the equipment’s proper installation and functionality.

Objective: To verify that the HEPA Integrity Test System is installed correctly and operates as intended according to specified criteria.

Scope: This protocol applies to the HEPA Integrity Test System (Photometer + Aerosol Generator) located in the Engineering area and is intended for use in testing HEPA filter integrity for sterile applications.

Responsibilities:

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Engineering Team: Responsible for equipment installation and maintenance.
  • Quality Assurance: Responsible for final review and approval of the IQ documentation.

Prerequisites:

  • Completion of equipment installation according to manufacturer specifications.
  • Availability of necessary tools and materials for testing.
  • Training of personnel on equipment operation and safety protocols.

Equipment Description:

The HEPA Integrity Test System consists of a photometer and aerosol generator designed to assess the integrity of HEPA filters used in sterile environments. This system evaluates the aerosol concentration scan method to determine pass/fail criteria in accordance with ISO14644 standards.

Test ID Procedure Acceptance Evidence
IQ-HEPA-001 Perform aerosol concentration scan using the photometer. Aerosol concentration meets pass/fail criteria as per ISO14644. Recorded data from the photometer.
IQ-HEPA-002 Verify calibration of the aerosol generator. Calibration within specified limits. Calibration certificate.
See also  Desiccant Inserter (if required) – DQ Protocol

Detailed Test Cases:

  1. Test Case 1: Verify installation of the photometer and aerosol generator.
  2. Test Case 2: Conduct aerosol concentration scan and document results.
  3. Test Case 3: Confirm calibration of the aerosol generator is within limits.

Deviations:

Any deviations from the acceptance criteria must be documented and investigated. Corrective actions should be implemented as necessary.

Approvals:

__________________________ Validation Team Lead

__________________________ Engineering Manager