Pneumatic Conveying (Dense Phase) – IQ Protocol

Installation Qualification Protocol for Pneumatic Conveying System

Document Control:

Version: 1.0

Effective Date: [Insert Date]

Reviewed by: [Insert Reviewer Name]

Approved by: [Insert Approver Name]

Objective

The objective of this Installation Qualification (IQ) protocol is to verify that the Pneumatic Conveying System is installed correctly and operates according to the defined specifications, ensuring compliance with URS Annex 11 standards.

Scope

This protocol applies to the Pneumatic Conveying System used for the contained transfer of solid dosage forms in the production area. It covers installation verification, operational checks, and data integrity assessments.

Responsibilities

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the IQ documentation.
  • Engineering: Responsible for ensuring the system is installed according to specifications.

Prerequisites

  • Completion of the equipment installation.
  • Availability of operation manuals and relevant documentation.
  • Training of personnel on the use of the Pneumatic Conveying System.

Equipment Description

The Pneumatic Conveying System (Dense Phase) is designed for the contained transfer of solid dosage forms with minimal segregation. It operates under controlled pressure and flow conditions to ensure product integrity during material transfer.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation per manufacturer’s specifications. Installation conforms to specifications. Installation checklist signed by Engineering.
IQ-02 Check electrical connections and grounding. All connections are secure and grounded. Electrical inspection report.
IQ-03 Confirm pressure settings on DP PLC. Pressure settings match specified parameters. Calibration certificate for pressure settings.
IQ-04 Test flow velocity at receiver. Flow velocity meets specified range. Flow velocity test results.
See also  Drum Tippler/Drum Tumbler – Traceability Matrix (URS ↔ Tests)

Detailed Test Cases

Test Case IQ-01

Objective: Verify installation per manufacturer’s specifications.

Procedure: Inspect all components and connections against the installation manual.

Acceptance Criteria: Installation conforms to specifications.

Evidence: Installation checklist signed by Engineering.

Test Case IQ-02

Objective: Check electrical connections and grounding.

Procedure: Inspect all electrical connections and verify grounding.

Acceptance Criteria: All connections are secure and grounded.

Evidence: Electrical inspection report.

Test Case IQ-03

Objective: Confirm pressure settings on DP PLC.

Procedure: Access the PLC and verify pressure settings.

Acceptance Criteria: Pressure settings match specified parameters.

Evidence: Calibration certificate for pressure settings.

Test Case IQ-04

Objective: Test flow velocity at receiver.

Procedure: Measure flow velocity during operation.

Acceptance Criteria: Flow velocity meets specified range.

Evidence: Flow velocity test results.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on product quality. A CAPA (Corrective and Preventive Action) may be required.

Approvals

Prepared by: [Insert Name]

Reviewed by: [Insert Name]

Approved by: [Insert Name]