Objective

The objective of this Design Qualification (DQ) protocol is to verify that the Rotary Sifter used for sifting powders in the production area meets the specified requirements and is suitable for its intended use.

Scope

This protocol applies to the Design Qualification of the Rotary Sifter used in the production of solid dosage forms (OSD) within the manufacturing facility.

Responsibilities

  • Validation Team: Responsible for executing the DQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the DQ protocol and results.
  • Engineering: Responsible for providing technical support and ensuring equipment compliance.

Prerequisites

  • Completion of User Requirements Specification (URS).
  • Installation Qualification (IQ) completed and approved.
  • Access to relevant standard operating procedures (SOPs).

Equipment Description

The Rotary Sifter is designed for sifting powders to ensure uniform particle size distribution. Key features include adjustable speed settings and a robust screen to maintain screen integrity during operation.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
T01 Verify speed settings during operation. Speed must be within specified range as per URS. Calibration records, speed test results.
T02 Check screen integrity before and after operation. No visible damage or wear on the screen. Photographic evidence, inspection report.

Detailed Test Cases

Test Case T01: Speed Verification

Procedure: Measure the speed of the Rotary Sifter using a calibrated tachometer during operation.

See also  Barcode Scanner (GMP) – PQ Protocol

Expected Result: Speed readings should match the specified range defined in the URS document.

Test Case T02: Screen Integrity Inspection

Procedure: Conduct a visual inspection of the sifter screen before and after use. Document any findings.

Expected Result: The screen should show no signs of damage or degradation.

Deviations

Any deviations from the acceptance criteria must be documented in the deviation log and reviewed by the Quality Assurance team for further action.

Approvals

Prepared by: ______________________ Date: ___________