Spheronizer / Marumerizer – DQ Protocol

Design Qualification Protocol for Spheronizer/Marumerizer in Solid Dosage Form

Document Number: DQ-OSD-001

Version: 1.0

Date: [Insert Date]

Prepared by: [Insert Name]

Reviewed by: [Insert Name]

Approved by: [Insert Name]

Objective

The objective of this Design Qualification (DQ) protocol is to verify that the Spheronizer/Marumerizer equipment is designed and installed in a manner that meets the specified requirements for solid dosage form production, ensuring compliance with regulatory standards.

Scope

This protocol applies to the Spheronizer/Marumerizer used in the production of pellets within the solid dosage form area. It encompasses the design, installation, and operational verification of the equipment.

Responsibilities

  • Validation Team: Responsible for the execution of the DQ protocol and documentation of results.
  • Quality Assurance: Responsible for review and approval of the DQ protocol and results.
  • Engineering: Responsible for installation and maintenance of the equipment.

Prerequisites

  • Completion of User Requirement Specification (URS).
  • Installation of Spheronizer/Marumerizer in designated production area.
  • Training of personnel on equipment operation and safety.

Equipment Description

The Spheronizer/Marumerizer is a piece of equipment utilized for the spheronization of pellets in solid dosage form production. It operates by transforming moist granules into spherical pellets, enhancing flow properties and uniformity.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
T1 Verify plate speed Within specified range as per URS Calibration report
T2 Measure time As per URS Time log
T3 Assess PSD shape Meets specifications outlined in URS PSD analysis report
See also  Extruder (Single Screw) – OQ Protocol

Detailed Test Cases

Test Case T1: Verify Plate Speed

Procedure: Measure the plate speed using a calibrated tachometer. Compare the measured value against the acceptance criteria defined in the URS.

Acceptance Criteria: Plate speed must be within the specified range.

Evidence: Calibration report documenting the plate speed measurement.

Test Case T2: Measure Time

Procedure: Record the time taken for the spheronization process. Ensure that it aligns with the time specified in the URS.

Acceptance Criteria: Time must match the specified duration.

Evidence: Time log maintained during the test.

Test Case T3: Assess PSD Shape

Procedure: Perform Particle Size Distribution (PSD) analysis on the produced pellets to evaluate their shape and size.

Acceptance Criteria: PSD shape must meet the specifications outlined in the URS.

Evidence: PSD analysis report detailing the results.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on product quality. A root cause analysis should be performed, and corrective actions must be implemented as necessary.

Approvals

Approved by: [Insert Name]

Date: [Insert Date]

“`