Design Qualification Protocol for Flake Crusher in Solid Dosage Form Production

Meta Description: This document outlines the Design Qualification Protocol for the Flake Crusher used in Solid Dosage Form production, detailing objectives, scope, responsibilities, and test plans.

Objective

The objective of this Design Qualification (DQ) protocol is to ensure that the Flake Crusher operates according to specified requirements and is suitable for its intended use in the production of solid dosage forms.

Scope

This protocol applies to the Flake Crusher used in the production area for dry granulation processes, specifically for crushing ribbons/flakes into smaller particles.

Responsibilities

The validation team is responsible for executing this protocol and ensuring compliance with all acceptance criteria. The Quality Assurance team will review and approve the results.

Prerequisites

1. Installation of the Flake Crusher in the designated production area.

2. Completion of the User Requirement Specification (URS).

3. Availability of qualified personnel for testing.

Equipment Description

The Flake Crusher is designed to crush ribbons/flakes generated from the roller compaction process into a specified particle size distribution (PSD). Key parameters include speed and screen output PSD.

Detailed Test Cases

Test Case 1: Verify Speed Settings

Procedure: Set the Flake Crusher to the specified speed and record the actual speed using a calibrated tachometer.

Acceptance Criteria: The recorded speed must be within the range specified in the URS.

Evidence: Calibration records and speed measurement logs.

Test Case 2: Measure Screen Output PSD

Procedure: Collect samples of crushed material and analyze particle size distribution using appropriate analytical methods.

Acceptance Criteria: The PSD must meet the specifications outlined in the URS.

Evidence: Particle size analysis report.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A corrective action plan should be developed and implemented as necessary.