Blister Packing Machine (Thermoform) – IQ Protocol

Document ID: IQ-BPM-001

Version: 1.0

Effective Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Installation Qualification Protocol for Blister Packing Machine

Objective: To verify that the Blister Packing Machine (Thermoform) is installed correctly and operates according to specified requirements for the packaging of solid dosage forms.

Scope: This protocol applies to the Installation Qualification of the Blister Packing Machine located in the Packaging/Primary area, which is utilized for blister packing tablets and capsules.

Responsibilities:

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Engineering: Responsible for providing technical support during the qualification process.

Prerequisites:

  • Installation of the Blister Packing Machine must be completed.
  • All utilities (water, electricity, air) must be verified and functional.
  • All necessary documentation (URS, design specifications) must be available.

Equipment Description:

The Blister Packing Machine (Thermoform) is designed for the efficient and reliable packaging of tablets and capsules in blister packs. Key critical parameters include:

  • Forming Temperature
  • Sealing Temperature
  • Dwell Time
  • Pressure
  • Reject PLC
Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of the machine components as per manufacturer specifications. All components installed as per specifications. Installation checklist signed by the engineering team.
IQ-02 Check utility connections (water, air, electricity). All utilities functional and meet specifications. Utility verification report.
IQ-03 Perform a calibration check on critical parameters. All parameters within defined limits. Calibration certificates and test results.
IQ-04 Conduct a dry run of the machine. Machine operates without errors. Dry run report.
See also  Peristaltic Pump (Binder Addition) – Deviation Impact Assessment

Detailed Test Cases:

  • Test ID: IQ-01: Confirm that all machine components are installed according to the manufacturer’s specifications. Document any discrepancies.
  • Test ID: IQ-02: Verify that all utility connections are functional. Log any issues encountered during verification.
  • Test ID: IQ-03: Ensure calibration of critical parameters (forming temp, sealing temp, dwell pressure) is within acceptance limits. Record calibration data.
  • Test ID: IQ-04: Execute a dry run to validate operational functionality. Document any errors or malfunctions.

Deviations: Any deviations from the acceptance criteria must be documented in the deviation log and assessed for impact on the validation process.

Approvals:

  • Prepared By: ____________________ Date: _____________
  • Reviewed By: ____________________ Date: _____________
  • Approved By: ____________________ Date: _____________

Data Integrity Checks:

  • Ensure that all data logged during testing is securely stored and backed up.
  • Verify that all electronic records are timestamped and attributed to the individual performing the test.
  • Conduct periodic reviews of data logs to ensure completeness and accuracy.