Bottle Unscrambler – IQ Protocol

Document Control:

Version: 1.0

Date: [Insert Date]

Prepared by: [Insert Name]

Reviewed by: [Insert Name]

Approved by: [Insert Name]

Installation Qualification Protocol for Bottle Unscrambler

Objective: To establish and document the Installation Qualification (IQ) for the Bottle Unscrambler used in the packaging area for solid dosage forms, ensuring compliance with user requirements and regulatory standards.

Scope: This protocol applies to the installation and qualification of the Bottle Unscrambler in the Packaging/Primary area, focusing on its use for bottle feeding and orientation.

Responsibilities:

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Ensures compliance with regulatory requirements and reviews the IQ documentation.
  • Maintenance Team: Assists in equipment installation and troubleshooting during the qualification process.

Prerequisites:

  • All installation materials and equipment are available.
  • Personnel are trained on equipment operation and safety procedures.
  • Applicable standard operating procedures (SOPs) are reviewed and available.

Equipment Description:

The Bottle Unscrambler is designed to feed and orient bottles into the packaging line. It operates with speed jam sensors and interlocks to ensure safe and efficient operation.

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of the Bottle Unscrambler in the designated area. Equipment is installed as per manufacturer specifications. Installation checklist completed.
IQ-02 Check electrical connections and ensure proper power supply. Power supply is stable and meets specifications. Electrical inspection report.
IQ-03 Test speed jam sensors and interlocks. All sensors and interlocks function correctly. Sensor test results.
See also  Multi Mill – Traceability Matrix (URS ↔ Tests)

Detailed Test Cases:

Test Case IQ-01:

  • Procedure: Confirm the Bottle Unscrambler is positioned correctly.
  • Acceptance Criteria: Equipment is aligned and secured as per specifications.
  • Evidence: Photographic documentation and signed installation checklist.

Test Case IQ-02:

  • Procedure: Measure voltage and current at the power supply.
  • Acceptance Criteria: Voltage and current readings are within specified limits.
  • Evidence: Electrical measurement logs.

Test Case IQ-03:

  • Procedure: Simulate a jam and verify sensor response.
  • Acceptance Criteria: Sensor triggers and interlock activates as intended.
  • Evidence: Test report detailing sensor performance.

Deviations: Any deviations from the protocol must be documented and justified in a deviation report.

Approvals:

  • [Insert Name], Validation Team Lead
  • [Insert Name], Quality Assurance Manager