Calibration Documents: Disintegration Tester (CAL-0131)
| Asset ID | CAL-0131 |
|---|---|
| Equipment | Disintegration Tester |
| Equipment Type | Disintegration Tester |
| Department | QC |
| Area/Location | Instrument Room |
| Process Use | Disintegration |
| Parameter | Temperature |
| Units | °C |
| Range Min | 20 |
| Range Max | 50 |
| Acceptance Criteria | ±0.5°C |
| Calibration Frequency (days) | 365 |
| Calibration Type | External |
| Traceability | ISO17025 |
Table of Contents
Calibration SOP
1. Purpose
The calibration of the Disintegration Tester (Asset ID: CAL-0131) is performed to ensure accurate measurement of temperature during the disintegration process. This is critical for maintaining patient safety, ensuring batch quality, and upholding data integrity. Accurate temperature readings help prevent deviations that could affect product efficacy and safety.
2. Scope
Asset ID: CAL-0131
Equipment Name/Type: Disintegration Tester
Department/Area: QC, Instrument Room
Process Use: Disintegration
Parameter: Temperature
Range: 20°C to 50°C
Units: °C
Calibration Frequency: 365 days
3. Definitions
- Calibration: The process of comparing a measurement instrument against a known standard to determine its accuracy.
- Verification: The process of confirming that a measurement instrument meets specified requirements.
- Adjustment: The process of modifying a measurement instrument to bring it into compliance with specifications.
- As Found: The condition of the instrument prior to any adjustments.
- As Left: The condition of the instrument after adjustments have been made.
- OOT (Out of Tolerance): A condition where a measurement falls outside the specified acceptance criteria.
- Drift: The gradual change in the output of a measurement instrument over time.
- Traceability: The ability to verify the history, location, or application of an item by means of documented recorded identification.
- Measurement Uncertainty: A parameter that characterizes the range of values within which the true value is asserted to lie.
- Intermediate Check: A periodic check of the instrument’s performance between calibrations.
4. References
- Company Metrology SOP [TBD]
- ISO/IEC 17025 traceability via calibration certificates
- ALCOA+ principles
5. Responsibilities
- Technician/Metrology: Perform calibration and document results.
- QC/QA Reviewer: Review calibration results and ensure compliance.
- Owner Department: Ensure equipment is available and maintained.
- External Service Provider: Conduct external calibration as per schedule.
6. Safety & Preconditions
- Ensure environmental controls are in place (temperature, humidity).
- Allow equipment to warm up and stabilize as per manufacturer’s instructions.
- Maintain cleanliness of the instrument and surrounding area.
- Check that the instrument is level and properly positioned.
- Verify power supply is stable and within specifications.
7. Standards & Tools
Reference Standards Required: [TBD]
Traceability Statement: ISO17025
Certificate Validity Check: Ensure calibration certificates are current and valid.
8. Calibration Strategy
Calibration will follow the As Found and As Left logic. The minimum number of test points will be five, including the endpoints (20°C and 50°C) and midpoints. Each point should have three replicate readings to ensure accuracy and reliability.
9. Step-by-Step Procedure
- Preparation: Gather all necessary tools and documentation.
- Stabilization: Allow the Disintegration Tester to stabilize at the operating temperature range.
- As Found checks and data capture: Measure temperature at specified points and record results contemporaneously.
- Adjustment rules: If any readings are OOT, follow the adjustment protocol; if adjustments are not permissible, escalate to QA.
- As Left verification: Re-measure to confirm that the instrument is within acceptance criteria after adjustments.
- Labeling + documentation completion: Complete all required documentation and label the instrument with calibration details.
10. Acceptance Criteria & Calculations
Acceptance Criteria: ±0.5°C
Error Calculation Formula: Error = Observed Value – True Value
Pass/Fail Logic: If the error falls within the acceptance criteria, the calibration passes; otherwise, it fails.
Rounding Rule: [TBD]
11. Handling OOT / Failures
- Immediate containment: Tag the equipment and cease use.
- Notification & deviation initiation: Notify QA and initiate deviation process.
- Impact assessment trigger: Define the impact window and review all affected results/batches.
- Recalibration after repair/adjustment: Ensure recalibration is performed post-adjustment.
- QA disposition placeholders: [TBD]
12. Records & Retention
Maintain logbook entries, calibration report/certificate filing, and e-records if applicable [TBD].
Label Content Requirements: Calibrated date, due date, technician name, and calibration status.
13. Annexures
Annexure A: Calibration Data Sheet (test points, reference, observed, error, acceptance, pass/fail; include As Found + As Left columns)
Annexure B: Quick checklist
Annexure C: Example label text (with [TBD] placeholders)
Calibration Protocol
Calibration Protocol
| Protocol ID | Asset ID | Equipment Name | Equipment Type | Dept | Area | Process Use | Parameter | Units | Range | Acceptance Criteria | Frequency | Calibration Type | Traceability |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| [TBD] | CAL-0131 | Disintegration Tester | Disintegration Tester | QC | Instrument Room | Disintegration | Temperature | °C | 20 – 50 | ±0.5°C | 365 days | External | ISO17025 |
Environmental Conditions
Temperature: [TBD] °C
Relative Humidity: [TBD]
Vibration: [TBD]
Drafts: [TBD]
Test Point Selection
- Minimum: 20°C
- 25%: 27.5°C
- 50%: 35°C
- 75%: 42.5°C
- Maximum: 50°C
Results Table
| Test Point | Ref Value | Observed (As Found) | Error | Limit | Pass/Fail | Observed (As Left) | Error | Pass/Fail |
|---|---|---|---|---|---|---|---|---|
| 20°C | 20°C | [TBD] | [TBD] | ±0.5°C | [TBD] | [TBD] | [TBD] | [TBD] |
| 27.5°C | 27.5°C | [TBD] | [TBD] | ±0.5°C | [TBD] | [TBD] | [TBD] | [TBD] |
| 35°C | 35°C | [TBD] | [TBD] | ±0.5°C | [TBD] | [TBD] | [TBD] | [TBD] |
| 42.5°C | 42.5°C | [TBD] | [TBD] | ±0.5°C | [TBD] | [TBD] | [TBD] | [TBD] |
| 50°C | 50°C | [TBD] | [TBD] | ±0.5°C | [TBD] | [TBD] | [TBD] | [TBD] |
Stepwise Instructions
- Preparation: Ensure the Disintegration Tester is clean and calibrated prior to use.
- Stabilization: Allow the equipment to stabilize at the ambient temperature for at least 30 minutes.
- Performing Readings:
- Set the Disintegration Tester to the first test point.
- Take three replicate readings for each test point.
- Calculating Error: Calculate the error for each observed value against the reference value.
- Evaluation: Compare the calculated error against the acceptance criteria.
- Documentation: Record all observations in the results table and ensure data integrity (ALCOA+).
Deviation Instruction for OOT
If any observed value falls outside the acceptance criteria:
- Stop use of the equipment immediately.
- Notify the Quality Assurance (QA) department.
- Open a deviation report.
- Quarantine impacted results window: [TBD]
- Await QA decision on further actions.
Approvals
| Prepared By | Reviewed By | Approved By |
|---|---|---|
| [Signature/Date] | [Signature/Date] | [Signature/Date] |
Calibration Checklist
| Asset ID | Equipment | Dept | Area | Parameter | Range | Acceptance | Frequency | Traceability |
|---|---|---|---|---|---|---|---|---|
| CAL-0131 | Disintegration Tester | QC | Instrument Room | Temperature | 20 – 50 °C | ±0.5°C | 365 days | ISO17025 |
Pre-calibration
- [ ] Verify environmental conditions are within specified limits
- [ ] Ensure equipment has warmed up adequately
- [ ] Clean the equipment as per SOP
- [ ] Level the equipment if necessary
- [ ] Confirm reference standards are valid and calibrated
- [ ] Ensure logbook is ready for documentation
As Found Execution
- [ ] Set temperature setpoints
- [ ] Perform repeat measurements as required
- [ ] Record raw data accurately
- [ ] Perform necessary calculations for results
OOT Immediate Actions
- [ ] Tag out the equipment
- [ ] Stop use of the equipment
- [ ] Notify the appropriate personnel
- [ ] Document deviation from acceptance criteria
- [ ] Trigger impact review as necessary
As Left Verification
- [ ] Conduct post-adjustment checks
- [ ] Confirm all measurements are within specified limits
Documentation & Closure
- [ ] Update equipment label with calibration details
- [ ] Attach calibration certificate to documentation
- [ ] Obtain reviewer sign-off
- [ ] Update next due date for calibration
Deviation Impact Assessment
| Event Summary |
|---|
|
Asset: Disintegration Tester Date: [TBD] Discovered By: [TBD] Document References: [TBD] As Found Results Summary: [TBD] |
Immediate Containment Checklist
- Stop use of the equipment
- Label/tag the equipment as out of service
- Segregate impacted work
Define Impact Window
| Last Known In-Tolerance Date | Discovery Date |
|---|---|
| [TBD] | [TBD] |
Product/Batch/Test Impact Review
| Batch/Study/Report ID | Results Potentially Impacted | Re-Test/Re-Weigh Decision |
|---|---|---|
| [TBD] | [TBD] | [TBD] |
Data Integrity Review Prompts (ALCOA+)
- Attributable: [TBD]
- Legible: [TBD]
- Contemporaneous: [TBD]
- Original: [TBD]
- Accurate: [TBD]
- Complete: [TBD]
- Consistent: [TBD]
- Enduring: [TBD]
- Available: [TBD]
Risk Assessment
| Severity | Probability | Detectability | Rationale | Overall Risk |
|---|---|---|---|---|
| [TBD] | [TBD] | [TBD] | [TBD] | [TBD] |
Investigation Summary
Root Cause: [TBD]
CAPA Plan
| Action | Owner | Due Date | Effectiveness Check |
|---|---|---|---|
| [TBD] | [TBD] | [TBD] | [TBD] |
QA Disposition
Release/Hold/Retest/Recall Triggers: [TBD]
Calibration Certificate
Certificate No: [TBD]
Date: [TBD]
Next Due Date: [TBD]
Asset Details
| Asset ID | Equipment Name | Equipment Type | Dept | Area | Make/Model | Serial No | Location | Parameter/Range/Units | Acceptance Criteria |
|---|---|---|---|---|---|---|---|---|---|
| CAL-0131 | Disintegration Tester | Disintegration Tester | QC | Instrument Room | [TBD] | [TBD] | [TBD] | Temperature: 20 – 50 °C | ±0.5°C |
Conditions
Environment: [TBD]
Reference Standards
| Standard Name/ID | Certificate No | Due Date | Traceability Statement |
|---|---|---|---|
| [TBD] | [TBD] | [TBD] | ISO17025 |
Results
As Found Results
| Test Point | Measurement (°C) | Pass/Fail |
|---|---|---|
| 1 | [TBD] | [TBD] |
| 2 | [TBD] | [TBD] |
| 3 | [TBD] | [TBD] |
| 4 | [TBD] | [TBD] |
| 5 | [TBD] | [TBD] |
As Left Results
| Test Point | Measurement (°C) | Pass/Fail |
|---|---|---|
| 1 | [TBD] | [TBD] |
| 2 | [TBD] | [TBD] |
| 3 | [TBD] | [TBD] |
| 4 | [TBD] | [TBD] |
| 5 | [TBD] | [TBD] |
Measurement Uncertainty Statement: [TBD]
Statement of Conformity: [Pass/Fail overall]
Remarks: [TBD]
Signatures
Performed by: ____________________ Date: __________
Checked by: ____________________ Date: __________
Approved by: ____________________ Date: __________