Stability Chamber Controller Display Temp (CAL-0182) – Calibration Documents

Calibration Documents: Stability Chamber Controller Display Temp (CAL-0182)

Asset ID CAL-0182
Equipment Stability Chamber Controller Display Temp
Equipment Type Temp Controller
Department Stability
Area/Location Stability Room
Process Use ICH stability
Parameter Temperature
Units °C
Range Min 0
Range Max 60
Acceptance Criteria ±0.5°C
Calibration Frequency (days) 365
Calibration Type External
Traceability ISO17025

Calibration SOP

1. Purpose

The calibration of the Stability Chamber Controller Display Temperature is performed to ensure accurate temperature readings within the stability room, which is critical for maintaining the integrity of stability studies as per ICH guidelines. This calibration controls risks related to accuracy, patient safety, batch quality, and data integrity.

2. Scope

  • Asset ID: CAL-0182
  • Equipment Name/Type: Stability Chamber Controller Display Temp / Temp Controller
  • Department/Area: Stability / Stability Room
  • Process Use: ICH stability
  • Parameter: Temperature
  • Range: 0°C to 60°C
  • Units: °C
  • Calibration Frequency: 365 days

3. Definitions

  • Calibration: The process of comparing a measurement instrument to a known standard to ensure accuracy.
  • Verification: The process of confirming that a measurement instrument is functioning correctly.
  • Adjustment: The act of correcting a measurement instrument to ensure it provides accurate readings.
  • As Found: The condition of the instrument prior to any adjustments.
  • As Left: The condition of the instrument after adjustments have been made.
  • OOT (Out of Tolerance): A condition where the measurement falls outside the defined acceptance criteria.
  • Drift: The gradual change in the accuracy of a measurement instrument over time.
  • Traceability: The ability to verify the history, location, or application of an item by means of documented recorded identification.
  • Measurement Uncertainty: A parameter that characterizes the range of values within which the true value of a measurement lies.
  • Intermediate Check: A quick assessment of the instrument’s performance between full calibrations.

4. References

  • Company Metrology SOP [TBD]
  • ISO/IEC 17025 traceability via calibration certificates
  • ALCOA+ principles

5. Responsibilities

  • Technician/Metrology: Perform calibration and maintain records.
  • QC/QA Reviewer: Review calibration records and ensure compliance.
  • Owner Department: Ensure equipment is available and in good condition for calibration.
  • External Service Provider: Conduct external calibrations as required.

6. Safety & Preconditions

  • Ensure environmental controls are in place (temperature, humidity).
  • Allow equipment to warm-up and stabilize as per manufacturer specifications.
  • Maintain cleanliness of the calibration area and equipment.
  • Check leveling of the equipment to ensure accurate readings.
  • Verify power supply is stable and within specifications.
See also  Autoclave Chart Recorder Pressure (CAL-0221) - Calibration Documents

7. Standards & Tools

  • Reference Standards Required: [TBD]
  • Traceability Statement: ISO17025
  • Certificate Validity Check: Ensure all calibration certificates are current and valid.
  • Standard ID: [TBD]

8. Calibration Strategy

Calibration will follow the As Found and As Left logic. The minimum number of points for calibration will be 5, including endpoints (0°C and 60°C) and midpoints (15°C, 30°C, and 45°C). Each point will have 3 replicate readings to ensure accuracy.

9. Step-by-Step Procedure

  1. Preparation: Gather all necessary tools and reference standards.
  2. Stabilization: Allow the stability chamber to reach the desired temperature range.
  3. As Found checks and data capture: Measure the temperature at each defined point and record the data contemporaneously.
  4. Adjustment rules: If OOT is found, escalate to the QA department for further action.
  5. As Left verification: Confirm that the instrument is within acceptance criteria after any adjustments.
  6. Labeling + documentation completion: Complete all required documentation and label the equipment with calibration details.

10. Acceptance Criteria & Calculations

The acceptance criteria for this calibration is ±0.5°C. The error calculation formula is:

Error = Observed Value – True Value

Pass/Fail logic: If the absolute value of the error is within the acceptance criteria, the calibration passes; otherwise, it fails.

Rounding rule: [TBD]

11. Handling OOT / Failures

  • Immediate containment: Tag the equipment and stop its use.
  • Notification & deviation initiation: Notify QA and initiate a deviation report.
  • Impact assessment trigger: Define the impact window and review affected results/batches.
  • Recalibration after repair/adjustment: Ensure recalibration is performed post-adjustment.
  • QA disposition placeholders: [TBD]

12. Records & Retention

  • Logbook entries: Document all calibration activities in the logbook.
  • Calibration report/certificate filing: Maintain a file of all calibration reports and certificates.
  • e-Records if applicable: [TBD]
  • Label content requirements: Include calibrated date, due date, technician name, and status.

13. Annexures

Annexure A: Calibration Data Sheet

Test Points Reference Observed Error Acceptance Pass/Fail As Found As Left
[TBD] [TBD] [TBD] [TBD] [TBD] [TBD] [TBD] [TBD]

Annexure B: Quick Checklist

  • Environmental controls verified
  • Equipment warmed up
  • Cleanliness checked
  • Leveling confirmed
  • Power supply stable

Annexure C: Example Label Text

Calibration Date: [TBD]

Due Date: [TBD]

Calibrated By: [TBD]

Status: [TBD]

⬆ Back to TOC

See also  GC-MS (CAL-0125) - Calibration Documents

Calibration Protocol

Calibration Protocol

Protocol ID Asset ID Equipment Name Equipment Type Dept Area Process Use Parameter Units Range Acceptance Criteria Frequency Calibration Type Traceability
[TBD] CAL-0182 Stability Chamber Controller Display Temp Temp Controller Stability Stability Room ICH stability Temperature °C 0 – 60 ±0.5°C 365 days External ISO17025

Environmental Conditions

Temperature: [TBD]

Relative Humidity: [TBD]

Vibration: [TBD]

Drafts: [TBD]

Test Point Selection

  • Minimum: 0°C
  • 25% of Range: 15°C
  • 50% of Range: 30°C
  • 75% of Range: 45°C
  • Maximum: 60°C

Results Table

Test Point Ref Value Observed (As Found) Error Limit Pass/Fail Observed (As Left) Error Pass/Fail
0°C [TBD] [TBD] [TBD] ±0.5°C [TBD] [TBD] [TBD] [TBD]
15°C [TBD] [TBD] [TBD] ±0.5°C [TBD] [TBD] [TBD] [TBD]
30°C [TBD] [TBD] [TBD] ±0.5°C [TBD] [TBD] [TBD] [TBD]
45°C [TBD] [TBD] [TBD] ±0.5°C [TBD] [TBD] [TBD] [TBD]
60°C [TBD] [TBD] [TBD] ±0.5°C [TBD] [TBD] [TBD] [TBD]

Stepwise Instructions

  1. Preparation: Ensure the stability chamber is clean and operational. Verify the calibration equipment is within its calibration date.
  2. Stabilization: Allow the stability chamber to stabilize at each test point for a minimum of [TBD] minutes.
  3. Performing Readings: Take at least three replicate readings at each test point to ensure accuracy.
  4. Calculating Error: Calculate the error for each observed value using the formula: Error = Observed – Ref Value.
  5. Evaluation: Compare the calculated error against the acceptance criteria of ±0.5°C.
  6. Documentation: Record all observations, calculations, and results in the results table.

Deviation Instruction for OOT

  • Stop use of the equipment immediately.
  • Notify the QA department.
  • Open a deviation report.
  • Quarantine impacted results window: [TBD]
  • Await QA decision on further actions.

Approvals

Prepared Reviewed Approved
[Signature/Date] [Signature/Date] [Signature/Date]

⬆ Back to TOC


Calibration Checklist

Asset ID Equipment Dept Area Parameter Range Acceptance Frequency Traceability
CAL-0182 Stability Chamber Controller Display Temp Stability Stability Room Temperature 0 to 60 °C ±0.5°C 365 days ISO17025

Pre-calibration

  • [ ] Verify environmental conditions are within acceptable limits
  • [ ] Ensure equipment has been powered on for the required warm-up period
  • [ ] Clean the equipment as per SOP
  • [ ] Level the equipment if necessary
  • [ ] Check validity of reference standards
  • [ ] Ensure calibration logbook is ready for documentation

As Found Execution

  • [ ] Record initial setpoints of the temperature controller
  • [ ] Perform repeat measurements to ensure consistency
  • [ ] Record all raw data accurately
  • [ ] Perform necessary calculations for data analysis
See also  Volumetric Flask 10 mL (CAL-0032) - Calibration Documents

OOT Immediate Actions

  • [ ] Tag out the equipment if out of tolerance (OOT)
  • [ ] Stop use of the equipment immediately
  • [ ] Notify the appropriate personnel
  • [ ] Document the deviation
  • [ ] Trigger impact review process

As Left Verification

  • [ ] Conduct post-adjustment checks to confirm accuracy
  • [ ] Ensure all measurements are within specified limits

Documentation & Closure

  • [ ] Update equipment label with calibration details
  • [ ] Attach calibration certificate to the logbook
  • [ ] Obtain reviewer sign-off on calibration documentation
  • [ ] Update next due date for calibration

Data Integrity (ALCOA+): Ensure all data recorded is attributable, legible, contemporaneous, original, and accurate. Maintain compliance with all applicable regulations.

⬆ Back to TOC


Deviation Impact Assessment

Event Summary
Asset: Stability Chamber Controller Display Temp
Date: [TBD]
Discovered By: [TBD]
Document References: [TBD]
As Found Results Summary: [TBD]

Immediate Containment Checklist

  • Stop use of the asset
  • Label/Tag the asset as out of service
  • Segregate impacted work

Define Impact Window

Last known in-tolerance date: [TBD] to discovery date: [TBD]

Product/Batch/Test Impact Review

Batch/Study/Report ID Results Potentially Impacted Re-test/Re-weigh Decision
[TBD] [TBD] [TBD]

Data Integrity Review Prompts (ALCOA+)

  • Attributable: [TBD]
  • Legible: [TBD]
  • Contemporaneous: [TBD]
  • Original: [TBD]
  • Accurate: [TBD]
  • Complete: [TBD]
  • Consistent: [TBD]
  • Enduring: [TBD]
  • Available: [TBD]

Risk Assessment

Severity Probability Detectability Rationale Overall Risk
[TBD] [TBD] [TBD] [TBD] [TBD]

Investigation Summary

Root Cause: [TBD]

CAPA Plan

Action Owner Due Date Effectiveness Check
[TBD] [TBD] [TBD] [TBD]

QA Disposition

Release/Hold/Retest/Recall Triggers: [TBD]

⬆ Back to TOC


Calibration Certificate

Certificate No: [TBD]

Date: [TBD]

Next Due Date: [TBD]

Asset Details

Asset ID Equipment Name Equipment Type Dept Area Make/Model Serial No Location Parameter/Range/Units Acceptance Criteria
CAL-0182 Stability Chamber Controller Display Temp Temp Controller Stability Stability Room [TBD] [TBD] [TBD] Temperature: 0 – 60 °C ±0.5°C

Conditions

Environment: [TBD]

Reference Standards

Standard Name/ID Certificate No Due Date Traceability Statement
[TBD] [TBD] [TBD] Traceability to ISO17025

Results

As Found Results

Test Point Measured Value (°C) Pass/Fail
1 [TBD] [TBD]
2 [TBD] [TBD]
3 [TBD] [TBD]
4 [TBD] [TBD]
5 [TBD] [TBD]

As Left Results

Test Point Measured Value (°C) Pass/Fail
1 [TBD] [TBD]
2 [TBD] [TBD]
3 [TBD] [TBD]
4 [TBD] [TBD]
5 [TBD] [TBD]

Measurement Uncertainty Statement: [TBD]

Statement of Conformity: [Pass/Fail overall]

Remarks: [TBD]

Signatures

Performed by: ______________________ Date: ___________

Checked by: ______________________ Date: ___________

Approved by: ______________________ Date: ___________

⬆ Back to TOC