Co-Mill / Conical Mill – OQ Protocol

Operational Qualification Protocol for Co-Mill/Conical Mill in Solid Dosage Form Production

Document Control:

Document Number: OQ-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Objective: To ensure that the Co-Mill/Conical Mill operates according to predetermined specifications and meets the acceptance criteria outlined in the User Requirement Specification (URS).

Scope: This protocol covers the operational qualification of the Co-Mill/Conical Mill used for de-agglomeration and sizing in the production of solid dosage forms.

Responsibilities:

  • Validation Team: Overall execution and documentation of the OQ protocol.
  • Production Team: Operation of the Co-Mill/Conical Mill during testing.
  • Quality Assurance: Review and approval of the OQ protocol and results.

Prerequisites:

  • Installation Qualification (IQ) must be completed and approved.
  • All personnel involved in the OQ must be trained on the equipment.

Equipment Description: The Co-Mill/Conical Mill is designed for the de-agglomeration and sizing of solid dosage forms. It utilizes an impeller to achieve desired particle size distribution (PSD) through adjustable screen sizes.

Test ID Procedure Acceptance Criteria Evidence
OQ-01 Verify impeller speed settings at specified RPM. Impeller speed must match the specified settings within ±5%. Calibration logs and speed measurements.
OQ-02 Check screen size installation and integrity. Screen size must match the specifications in the URS. Visual inspection and documentation of screen size.
OQ-03 Measure output PSD after milling. Output PSD must fall within the defined range in the URS. PSD analysis report.
See also  OOE Full Form in Pharma: Out of Expectation (Meaning & Use)

Detailed Test Cases:

Test Case OQ-01: Impeller Speed Verification

Objective: To verify that the impeller speed settings are within the acceptable range.

Procedure: Operate the Co-Mill at designated RPM settings and record the actual speed using a tachometer.

Acceptance Criteria: Impeller speed must match the specified settings within ±5%.

Evidence: Calibration logs and speed measurements will be documented.

Test Case OQ-02: Screen Size Integrity Check

Objective: To ensure the correct screen size is installed and in good condition.

Procedure: Inspect the installed screen for the correct size and any signs of wear or damage.

Acceptance Criteria: Screen size must match the specifications in the URS.

Evidence: Visual inspection results will be documented.

Test Case OQ-03: Output PSD Measurement

Objective: To measure the particle size distribution of the output.

Procedure: Collect samples post-milling and analyze using a suitable particle size analyzer.

Acceptance Criteria: Output PSD must fall within the defined range in the URS.

Evidence: PSD analysis report will be attached.

Deviations: Any deviations from the acceptance criteria will be documented and assessed for impact on product quality.

Approvals:

Prepared By: ____________________ Date: ___________

Approved By: ____________________ Date: ___________