Performance Qualification Protocol for Conductivity Meter

Document Control:

Document Number: PQ-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approved By: [Insert Name]

Objective

The objective of this Performance Qualification (PQ) protocol is to validate the Conductivity Meter used in the QC Laboratory to ensure it meets specified performance criteria and complies with regulatory standards.

Scope

This protocol applies to the Conductivity Meter utilized in the QC Lab for direct conductivity measurements impacting product quality. It encompasses the validation process, including performance testing and data integrity checks.

Responsibilities

Validation Team: Responsible for executing the PQ protocol and documenting results.

Quality Assurance: Responsible for reviewing and approving the PQ protocol and results.

Laboratory Personnel: Responsible for operating the Conductivity Meter according to SOPs and participating in the validation process.

Prerequisites

Ensure that the Conductivity Meter is installed, operational, and calibrated according to the manufacturer’s specifications and internal SOPs prior to executing this PQ protocol.

Equipment Description

The Conductivity Meter is an instrument used for measuring the conductivity of liquids. It is critical for ensuring the quality and compliance of products within the QC Lab.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
TP-01 Conduct Accuracy Calibration Audit Trail Calibration meets specifications as per URS Annex 11 Calibration records, Audit trail report

Deviations

Any deviations from the protocol must be documented and justified. If acceptance criteria are not met, a root cause analysis should be conducted, and corrective actions must be implemented.

Approvals

This protocol must be approved by the Quality Assurance department before execution. All results must be reviewed and approved upon completion of the PQ testing.

Data Integrity Checks

Ensure that:

  • All data entries are timestamped.
  • Access to data is restricted to authorized personnel only.
  • Audit trails are maintained for all data alterations.
  • Regular backups are performed to prevent data loss.