Continuous Blender – PQ Protocol

Document Control:

Document Number: PQ-OSD-CB-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Performance Qualification Protocol for Continuous Blender in Solid Dosage Form Production

Objective: To validate the performance of the Continuous Blender used in the production of solid dosage forms, ensuring that it meets specified requirements and operates within defined parameters.

Scope: This protocol applies to the Continuous Blender utilized in the production area for continuous blending of solid dosage forms. It encompasses all critical parameters affecting product quality.

Responsibilities:

  • Validation Team: Responsible for executing the PQ protocol and documenting results.
  • Quality Assurance: Ensures compliance with relevant guidelines and reviews documentation.
  • Production Team: Provides operational support and assists in the execution of the protocol.

Prerequisites:

  • Completion of Installation Qualification (IQ) and Operational Qualification (OQ).
  • Availability of all necessary equipment and materials for testing.
  • Training of personnel on equipment operation and safety procedures.

Equipment Description: The Continuous Blender is designed for the continuous blending of solid dosage forms, allowing for efficient mixing of powders and granules. It operates under controlled feed rates, with real-time data monitoring through PLC controls.

Test ID Procedure Acceptance Criteria Evidence
PQ-01 Verify feed rates at specified RPM. Feed rates within ±5% of target. Calibration report and observation log.
PQ-02 Monitor RTD during operation. RTD readings consistent with expected values. RTD data logs.
PQ-03 Validate PLC control parameters. All PLC controls functioning correctly. PLC control logs and screenshots.
See also  Co-Mill / Conical Mill – IQ Protocol

Detailed Test Cases:

  • Test Case PQ-01: Execute blending at specified feed rates and record the actual rates. Compare against the target rates to ensure compliance.
  • Test Case PQ-02: Continuously monitor RTD during blending and document any deviations from expected values.
  • Test Case PQ-03: Test all PLC control functions, ensuring that all commands are executed as intended and document the results.

Deviations: Any deviations from the acceptance criteria must be documented and reviewed by the validation team and quality assurance. A corrective action plan must be created and implemented.

Approvals:

  • Validated By: [Insert Name], [Insert Title]
  • Approved By: [Insert Name], [Insert Title]

Data Integrity Checks:

  • Ensure all data is logged in real-time and backed up securely.
  • Conduct periodic audits of data logs to confirm accuracy.
  • Implement user access controls to prevent unauthorized data manipulation.