Distillation Unit / Distillation Column – IQ Protocol

Installation Qualification Protocol for Distillation Unit

Document Control:

Version: 1.0

Date: [Insert Date]

Prepared by: [Insert Name]

Approved by: [Insert Name]

Objective

The objective of this Installation Qualification (IQ) is to verify that the Distillation Unit is installed correctly and operates according to the specified requirements to ensure solvent purification and recovery in the API manufacturing process.

Scope

This protocol applies to the Installation Qualification of the Distillation Unit located in the Production area used for solvent purification or recovery, impacting product quality directly.

Responsibilities

Validation Team: Responsible for developing and executing the IQ protocol.

Quality Assurance: Responsible for reviewing and approving the protocol and results.

Maintenance Team: Responsible for ensuring the equipment is operational and maintained according to the specifications.

Prerequisites

1. Equipment must be installed according to the manufacturer’s specifications.

2. All necessary utilities (water, electricity, etc.) must be available and functioning.

3. Personnel must be trained on equipment operation and safety procedures.

Equipment Description

The Distillation Unit is designed for solvent purification or recovery through chemical synthesis and purification processes. It includes a distillation column, temperature controls, pressure gauges, and a PLC with audit trail logs.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-001 Verify installation against manufacturer specifications. All components are installed as per specifications. Installation checklist signed off.
IQ-002 Check utility connections (water, power). Utilities are functioning without leaks. Utility verification log.
IQ-003 Verify PLC audit trail functionality. Audit trail logs are recording events accurately. Audit trail report.
IQ-004 Test critical parameters: temp, pressure, reflux ratio. Parameters within specified limits. Test results log.
See also  Co-Mill / Conical Mill – Qualification Certificate Template

Detailed Test Cases

Test Case: IQ-001

Procedure: Inspect all components of the Distillation Unit to ensure they are installed according to the manufacturer’s specifications.

Acceptance Criteria: All components are present and correctly installed.

Evidence: Installation checklist signed by the validation team.

Test Case: IQ-002

Procedure: Verify all utility connections are secure and functioning.

Acceptance Criteria: No leaks detected, and utilities operational.

Evidence: Utility verification log signed by maintenance personnel.

Test Case: IQ-003

Procedure: Review PLC audit trail for accuracy in recording.

Acceptance Criteria: Audit trail logs show all expected events.

Evidence: PLC audit trail report.

Test Case: IQ-004

Procedure: Measure temperature, pressure, and reflux ratio during operation.

Acceptance Criteria: All parameters must be within defined limits.

Evidence: Test results log with recorded parameters.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on the validation process. Follow the established deviation management procedures for resolution.

Approvals

Prepared by: ______________________ Date: ___________

Reviewed by: ______________________ Date: ___________

Approved by: ______________________ Date: ___________

Data Integrity Checks

1. Ensure all data entries in the PLC audit trail are timestamped and user-identified.

2. Perform periodic reviews of data logs to identify any inconsistencies.

3. Implement automated alerts for any parameter deviations beyond acceptable limits.