Flake Crusher (Post-Roller Compaction) – IQ Protocol

Installation Qualification Protocol for Flake Crusher in Solid Dosage Form Production

Document ID: IQ-FC-001

Version: 1.0

Effective Date: [Insert Date]

Prepared by: [Your Name]

Reviewed by: [Reviewer Name]

Approved by: [Approver Name]

Objective

The objective of this Installation Qualification (IQ) protocol is to verify that the Flake Crusher is installed correctly and operates in accordance with the specified requirements for solid dosage form production.

Scope

This protocol applies to the Flake Crusher used in the production area for dry granulation processes involving solid dosage forms.

Responsibilities

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the IQ documentation.
  • Maintenance Team: Responsible for ensuring the equipment is maintained and operational during the IQ process.

Prerequisites

  • Completion of equipment installation and utilities connection.
  • All relevant training completed by personnel involved in the IQ process.
  • Availability of all necessary documentation, including URS and equipment manuals.

Equipment Description

The Flake Crusher is designed to crush ribbons and flakes produced from the roller compaction process. It is critical for ensuring uniform particle size distribution in solid dosage forms.

Test Plan

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify installation of the Flake Crusher. All components installed as per manufacturer’s specifications. Installation checklist and photographs.
IQ-02 Check alignment and leveling of the equipment. Equipment is level within 1 degree. Leveling report.
IQ-03 Verify electrical and mechanical connections. All connections meet safety and operational standards. Connection verification report.
IQ-04 Test operational parameters (speed, screen output, PSD). Speed: [specify]; Screen output: [specify]; PSD: [specify]. Operational test results.
See also  Capsule Checkweigher – Deviation Impact Assessment

Detailed Test Cases

Test Case: IQ-01

Procedure: Conduct a walkthrough of the Flake Crusher installation site and verify that all components are installed as per the manufacturer’s specifications.

Acceptance Criteria: All components installed as per manufacturer’s specifications.

Evidence: Installation checklist and photographs.

Test Case: IQ-02

Procedure: Use a leveling tool to ensure the Flake Crusher is level.

Acceptance Criteria: Equipment is level within 1 degree.

Evidence: Leveling report.

Test Case: IQ-03

Procedure: Inspect all electrical and mechanical connections for compliance with safety standards.

Acceptance Criteria: All connections meet safety and operational standards.

Evidence: Connection verification report.

Test Case: IQ-04

Procedure: Operate the equipment and measure speed, screen output, and particle size distribution (PSD).

Acceptance Criteria: Speed: [specify]; Screen output: [specify]; PSD: [specify].

Evidence: Operational test results.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A corrective action plan should be developed and implemented as necessary.

Approvals

The completion of this Installation Qualification protocol must be approved by the Quality Assurance department and relevant stakeholders.