Objective
The objective of this Operational Qualification (OQ) protocol is to verify that the -20°C Freezer used for the storage of raw materials operates within specified parameters and meets the acceptance criteria outlined in the User Requirement Specification (URS) Annex 11 and Annex 15.
Scope
This protocol applies to the -20°C Freezer located in the warehouse designated for the storage of frozen materials. It encompasses all critical parameters and operational functions necessary for compliance.
Responsibilities
- Validation Team: Responsible for executing the OQ protocol and documenting results.
- Quality Assurance: Responsible for reviewing and approving the protocol and results.
- Warehouse Manager: Responsible for ensuring the freezer is maintained and operational during the qualification process.
Prerequisites
- Freezer installed and operational.
- Calibration certificates for temperature monitoring devices.
- Standard Operating Procedures (SOPs) for equipment operation and maintenance.
Equipment Description
The -20°C Freezer is designed for the storage of raw materials that require frozen conditions. It features temperature mapping capabilities, alarm systems, and an audit trail for monitoring temperature fluctuations.
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| OQ-001 | Temperature Mapping | Temperature remains within -20°C ± 2°C | Mapping report |
| OQ-002 | Alarm Functionality Test | Alarms activate within 1 minute of deviation | Alarm test log |
| OQ-003 | Audit Trail Verification | Audit trail records all temperature deviations | Audit trail report |
Detailed Test Cases
Test Case OQ-001: Temperature Mapping
Conduct temperature mapping using calibrated data loggers placed at various locations within the freezer. Document temperature readings over a 24-hour period.
Test Case OQ-002: Alarm Functionality Test
Simulate temperature deviations by adjusting the thermostat. Verify that alarms activate and document the response time.
Test Case OQ-003: Audit Trail Verification
Review the audit trail for the past month to ensure all temperature deviations are recorded and assess the integrity of data logging.
Deviations
Any deviations from the acceptance criteria must be documented, investigated, and resolved prior to protocol approval. Non-conformances will be addressed in a deviation report.
Approvals