Glass Lined Reactor (GLR) – PQ Protocol

Document Control:

Document Number: PQ-GLR-001

Version: 1.0

Date: 2023-10-01

Prepared By: [Your Name]

Approved By: [Approver’s Name]

Performance Qualification Protocol for Glass Lined Reactor in API Manufacturing

Meta Description: This document outlines the Performance Qualification (PQ) protocol for the Glass Lined Reactor used in API manufacturing, covering critical parameters and acceptance criteria.

Tags: Equipment Validation, Performance Qualification, API Manufacturing, Glass Lined Reactor

Objective

The objective of this Performance Qualification (PQ) protocol is to verify that the Glass Lined Reactor (GLR) operates consistently and reliably within specified limits to ensure product quality and compliance with regulatory standards.

Scope

This protocol applies to the Glass Lined Reactor utilized in the chemical synthesis and purification of Active Pharmaceutical Ingredients (APIs) within the production area.

Responsibilities

The Validation Team is responsible for executing the PQ protocol, documenting results, and ensuring compliance with all applicable regulations. The Production Team will assist in the execution of the tests and provide necessary data.

Prerequisites

All prior validation activities, including Installation Qualification (IQ) and Operational Qualification (OQ), must be completed and documented before commencing this PQ protocol.

Equipment Description

The Glass Lined Reactor is designed for chemical synthesis reactions, featuring a robust glass lining to prevent contamination and facilitate easy cleaning. Key features include:

  • Temperature Control
  • Pressure Regulation
  • Agitation System
  • PLC Control System with Audit Trail

Test Plan

Test ID Procedure Acceptance Criteria Evidence
TP-001 Verify temperature control functionality Temperature within ±2°C of set point Temperature logs
TP-002 Verify pressure control functionality Pressure within ±5 psi of set point Pressure logs
TP-003 Verify agitation system performance Agitation speed within ±10% of set point Agitation logs
TP-004 Verify PLC control and audit trail Audit trail records all operations without gaps PLC audit trail report
See also  Serialization & Aggregation System – IQ Protocol

Detailed Test Cases

Test Case 1: Temperature Control

Procedure: Set the reactor to a designated temperature and monitor for stability over 30 minutes. Record values at 5-minute intervals.

Expected Result: Temperature remains within ±2°C of the set point throughout the duration.

Test Case 2: Pressure Control

Procedure: Set the reactor to a designated pressure and monitor for stability over 30 minutes. Record values at 5-minute intervals.

Expected Result: Pressure remains within ±5 psi of the set point throughout the duration.

Test Case 3: Agitation System

Procedure: Set the reactor to a designated agitation speed and monitor for consistency over 30 minutes. Record values at 5-minute intervals.

Expected Result: Agitation speed remains within ±10% of the set point throughout the duration.

Test Case 4: PLC Control and Audit Trail

Procedure: Review the PLC audit trail for all operations during the test period.

Expected Result: The audit trail shows continuous logging of all operations without gaps.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A corrective action plan must be implemented to address any identified issues.

Approvals

By signing below, the following individuals approve this Performance Qualification protocol:

Prepared By: ______________________ Date: ___________

Approved By: ______________________ Date: ___________

Data Integrity Checks

Ensure that all recorded data is backed up and stored securely. Conduct regular audits of data logs to confirm accuracy and completeness.