| URS ID | URS Statement | Risk (H/M/L) | DQ Test Ref | IQ Test Ref | OQ Test Ref | PQ Test Ref | Evidence/Record | Result |
|---|---|---|---|---|---|---|---|---|
| URS-001 | The induction sealing machine must effectively seal liners. | H | DQ-001 | IQ-001 | OQ-001 | PQ-001 | Seal Integrity Report | Pass |
| URS-002 | The machine must operate within specified power conveyor speed. | M | DQ-002 | IQ-002 | OQ-002 | PQ-002 | Speed Calibration Log | Pass |
| URS-003 | Seal integrity must be validated under various conditions. | H | DQ-003 | IQ-003 | OQ-003 | PQ-003 | Validation Summary Report | Pass |
| URS-004 | The machine must be capable of adjusting seal parameters. | L | DQ-004 | IQ-004 | OQ-004 | PQ-004 | Adjustment Log | Pass |