Document Control
Document Number: IQ-001
Version: 1.0
Date: [Insert Date]
Prepared By: [Insert Name]
Approved By: [Insert Name]
Installation Qualification Protocol for Jacketed Mixing Vessel
Objective
The objective of this Installation Qualification (IQ) protocol is to verify that the Jacketed Mixing Vessel is installed correctly and operates as intended for the manufacturing of creams, gels, and lotions.
Scope
This protocol applies to the Installation Qualification of the Jacketed Mixing Vessel located in the Production/Manufacturing area. It covers the verification of equipment installation, functionality, and compliance with the User Requirement Specification (URS) Annex 11.
Responsibilities
- Validation Team: Responsible for executing the IQ protocol and documenting results.
- Quality Assurance: Responsible for reviewing and approving the IQ documentation.
- Maintenance Team: Responsible for ensuring the equipment is installed according to specifications.
Prerequisites
- Completion of equipment installation.
- Availability of all necessary documentation (URS, manuals, etc.).
- Personnel trained in operating the equipment.
Equipment Description
The Jacketed Mixing Vessel is a stainless steel vessel designed for the mixing of semi-solids such as creams, ointments, gels, and lotions. The vessel is equipped with temperature control, agitation capabilities, and PLC logging for process monitoring.
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| IQ-01 | Verify installation of temperature control system. | Temperature control operates within specified range. | Calibration logs, temperature readings. |
| IQ-02 | Check agitation speed functionality. | Agitation speed meets specified RPM. | PLC logs, speed calibration results. |
| IQ-03 | Confirm hold time accuracy. | Hold time is maintained as per specifications. | Log records, temperature and time readings. |
Detailed Test Cases
Test Case: IQ-01
Objective: Verify the installation of the temperature control system.
Procedure: Check the wiring and connections of the temperature control system. Power on the system and set the temperature to the desired setpoint. Monitor the temperature readings.
Acceptance Criteria: The temperature control system must operate within the specified range as per the URS Annex 11.
Evidence: Calibration logs and temperature readings must be documented.
Test Case: IQ-02
Objective: Check the agitation speed functionality.
Procedure: Start the agitation system and measure the RPM using a tachometer. Compare the reading with the specified RPM in the URS.
Acceptance Criteria: Agitation speed must meet the specified RPM.
Evidence: PLC logs and speed calibration results must be recorded.
Test Case: IQ-03
Objective: Confirm hold time accuracy.
Procedure: Set the vessel to the specified hold time and monitor the duration. Record the temperature and time during the hold period.
Acceptance Criteria: Hold time must be maintained as per specifications.
Evidence: Log records including temperature and time readings must be documented.
Deviations
Any deviations from the acceptance criteria must be documented, along with the rationale and corrective actions taken.
Approvals
Prepared By: [Insert Name] – [Insert Title]
Approved By: [Insert Name] – [Insert Title]
Data Integrity Checks
- Ensure that all PLC logs are saved and backed up at the end of the qualification.
- Verify that temperature and agitation data are recorded in real-time.
- Conduct periodic reviews of the data logs for accuracy and completeness.