Design Qualification Protocol for Nasal Spray Filling Machine

Objective: To establish and document the Design Qualification (DQ) for the Nasal Spray Filling Machine, ensuring it meets the specified requirements for filling nasal spray bottles in a controlled production environment.

Scope: This protocol applies to the Nasal Spray Filling Machine used in the production area for the filling of sterile and non-sterile nasal spray products. It covers the validation of equipment critical to product quality and compliance with applicable regulations.

Responsibilities:

  • Validation Team: Prepare and execute the DQ protocol.
  • Quality Assurance: Review and approve the DQ protocol and results.
  • Production Team: Provide operational input and support during the qualification process.

Prerequisites:

  • Completion of User Requirement Specification (URS).
  • Installation Qualification (IQ) and Operational Qualification (OQ) protocols must be planned.
  • Availability of necessary documentation and training for personnel.

Equipment Description:

The Nasal Spray Filling Machine is designed for filling nasal spray bottles with precise accuracy. It operates in a controlled environment to ensure product sterility and compliance with regulatory requirements. Key features include:

  • Fill accuracy reject logic
  • Audit trail for process monitoring
Test ID Procedure Acceptance Criteria Evidence
DQ-01 Verify fill accuracy of the machine. Fill accuracy within +/- 5% of target volume. Calibration report and test results.
DQ-02 Check reject logic functionality. Machine must reject out-of-spec fills. Test results and machine log.
DQ-03 Review audit trail for compliance. Audit trail must show all operations and events. Audit trail report.
See also  Vacuum Degassing System – Validation Summary Report (VSR) Template

Detailed Test Cases:

  1. Test Case ID: DQ-01-01
    • Objective: To verify the fill accuracy.
    • Procedure: Conduct fill tests using calibrated measuring devices.
    • Expected Result: All fills within specified accuracy limits.
  2. Test Case ID: DQ-02-01
    • Objective: To ensure reject logic functions correctly.
    • Procedure: Simulate out-of-spec fills and observe machine behavior.
    • Expected Result: Machine rejects out-of-spec fills as intended.
  3. Test Case ID: DQ-03-01
    • Objective: To confirm the audit trail captures all relevant data.
    • Procedure: Review the audit trail for completeness post-testing.
    • Expected Result: Audit trail reflects all operations and events accurately.

Deviations: Any deviations from the acceptance criteria or procedures must be documented and assessed for impact on product quality and compliance. A deviation report must be submitted for review and approval.