Objective
The objective of this protocol is to validate the operational performance of the Nasal Spray Filling Machine to ensure it meets the defined acceptance criteria and operates within specified parameters.
Scope
This protocol applies to the Nasal Spray Filling Machine used in the production area for filling nasal spray bottles with sterile and non-sterile products.
Responsibilities
- Validation Team: Responsible for executing the protocol and documenting results.
- Quality Assurance: Responsible for reviewing and approving the protocol and results.
- Production Personnel: Responsible for operating the equipment according to SOPs.
Prerequisites
- Completion of Installation Qualification (IQ).
- Training of personnel on the operation of the Nasal Spray Filling Machine.
- Availability of necessary materials and equipment for testing.
Equipment Description
The Nasal Spray Filling Machine is designed to fill nasal spray bottles with precise volumes of liquid. It includes features for fill accuracy, reject logic, and an audit trail for traceability.
Test Plan
| Test ID | Procedure | Acceptance Criteria | Evidence |
|---|---|---|---|
| OQ-01 | Verify fill accuracy | Fill volume within ±5% of target | Calibration report, filled samples |
| OQ-02 | Audit trail verification | Audit trail logs are complete and accurate | Audit trail report |
| OQ-03 | Reject logic testing | Reject logic activates for out-of-spec fills | Test log, filled samples |
Detailed Test Cases
Test Case OQ-01: Verify Fill Accuracy
Procedure: Conduct fill tests at different volume settings and measure the actual fill volumes.
Acceptance Criteria: All filled volumes must be within ±5% of the target volume.
Evidence: Documented measurements and calibration reports.
Test Case OQ-02: Audit Trail Verification
Procedure: Review the audit trail logs for completeness and accuracy.
Acceptance Criteria: All entries must be present and correctly timestamped.
Evidence: Printed audit trail reports.
Test Case OQ-03: Reject Logic Testing
Procedure: Simulate out-of-spec fills and verify that the reject logic activates.
Acceptance Criteria: The machine must reject any fill that is not within specified limits.
Evidence: Test logs and observations during testing.
Deviations
Any deviations from the acceptance criteria must be documented and investigated. A root cause analysis should be performed, and corrective actions must be implemented.