Ointment Tube Filling Machine (Sterile/Controlled) – PQ Protocol

Document Control:

Document Number: PQ-OTF-001

Version: 1.0

Effective Date: YYYY-MM-DD

Review Date: YYYY-MM-DD

Prepared By: [Name]

Approved By: [Name]

Performance Qualification Protocol for Ointment Tube Filling Machine

Meta Description: This document outlines the Performance Qualification (PQ) protocol for the Ointment Tube Filling Machine used in the production of sterile ophthalmic products, ensuring compliance with regulatory standards.

Tags: Equipment Validation, Performance Qualification, Ophthalmics, Sterile Products

Objective

The objective of this Performance Qualification (PQ) protocol is to verify that the Ointment Tube Filling Machine operates according to its intended use and meets the defined acceptance criteria for filling ointment into ophthalmic tubes.

Scope

This protocol applies to the Ointment Tube Filling Machine used in the Production/Packaging area for the direct filling of sterile eye ointments. It covers the validation of critical parameters impacting product quality.

Responsibilities

The following roles are responsible for the execution of this protocol:

  • Validation Team: Overall execution and documentation of the PQ.
  • Quality Assurance: Review and approval of the PQ results.
  • Production Personnel: Operation of the equipment during testing.

Prerequisites

  • Completion of Installation Qualification (IQ) and Operational Qualification (OQ).
  • Training of personnel on equipment operation.
  • Availability of all necessary materials and equipment.

Equipment Description

The Ointment Tube Filling Machine is designed for the sterile filling of ophthalmic ointments into tubes. It operates under controlled conditions to ensure the integrity of the product and the filling process.

See also  Inline Static Mixer (if used) – Traceability Matrix (URS ↔ Tests)

Test Plan

Test ID Procedure Acceptance Evidence
PQ-01 Verify fill weight Fill weight within ±5% of target Weight logs
PQ-02 Check sealing integrity No leaks observed Leak test results
PQ-03 Audit reject trail All rejects logged and investigated Audit trail report

Detailed Test Cases

Test Case PQ-01: Verify Fill Weight

Procedure: Fill a predetermined number of tubes and measure the weight of each. Compare the results against the target fill weight.

Acceptance Criteria: All measurements must be within ±5% of the target weight.

Evidence: Documented fill weight measurements and calculations.

Test Case PQ-02: Check Sealing Integrity

Procedure: Conduct a sealing integrity test using a standardized method to ensure no leaks are present in the filled tubes.

Acceptance Criteria: No leaks should be detected during the test.

Evidence: Sealing integrity test results and photographs of the test setup.

Test Case PQ-03: Audit Reject Trail

Procedure: Review the reject logs generated during the filling process to ensure all rejects are documented and investigated.

Acceptance Criteria: All rejects must be logged with appropriate corrective actions noted.

Evidence: Audit trail report and investigation records.

Data Integrity Checks

As CSV is required, the following data integrity checks will be performed:

  • Validation of data entry points for accuracy.
  • Audit trails to track changes in filled weights and sealing integrity results.
  • Regular review of data logs to ensure compliance with acceptance criteria.

Deviations

Any deviations from the established acceptance criteria must be documented, along with the rationale and corrective actions taken. A deviation report must be submitted for review.

Approvals

This protocol will be approved by the following individuals:

  • Prepared By: [Name]
  • Reviewed By: [Name]
  • Approved By: [Name]