Ophthalmic Ointment Manufacturing Vessel (Sigma/Planetary/Vacuum) – OQ Protocol

Document Control:

Protocol Number: OQ-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Operational Qualification Protocol for Ophthalmic Ointment Manufacturing Vessel

Objective: To validate the operational performance of the Ophthalmic Ointment Manufacturing Vessel to ensure compliance with the required specifications for the preparation of sterile and non-sterile ointment bases.

Scope: This protocol applies to the operational qualification of the Ophthalmic Ointment Manufacturing Vessel used in the production area for the preparation of sterile/non-sterile ointments.

Responsibilities:

  • Validation Team: Prepare and execute the OQ protocol.
  • Quality Assurance: Review and approve the OQ protocol and results.
  • Production Team: Provide support during testing and ensure equipment availability.

Prerequisites:

  • Installation Qualification (IQ) must be completed and approved.
  • All required training for personnel must be completed.
  • All equipment must be calibrated and maintained according to standard operating procedures.

Equipment Description:

The Ophthalmic Ointment Manufacturing Vessel is designed for the preparation of sterile and non-sterile ointment bases. It features a vacuum mixing capability, temperature control, and torque measurement systems, integrated with PLC for data logging.

Test ID Procedure Acceptance Criteria Evidence
OQ-01 Verify temperature control functionality. Temperature within specified range (e.g., 20-25°C). Temperature log records.
OQ-02 Verify vacuum operation. Vacuum level meets specifications. Vacuum gauge readings.
OQ-03 Verify mixing speed settings. Mixing speed within specified range (e.g., 100-500 RPM). Mixing speed log records.
OQ-04 Verify torque measurement. Torque within specified range. Torque measurement records.
OQ-05 Review PLC logs for data integrity. All logs must be complete and accurate. PLC log reports.
See also  Fitz Mill / Comminuting Mill – PQ Protocol

Detailed Test Cases:

  • Test Case OQ-01: Conduct a temperature check during operation. Record the temperature at five-minute intervals for one hour. Compare with acceptance criteria.
  • Test Case OQ-02: Activate the vacuum system and monitor the gauge. Record readings at five-minute intervals until stable. Confirm against specifications.
  • Test Case OQ-03: Set the mixing speed to various levels and record the actual speed. Ensure it aligns with the set parameters.
  • Test Case OQ-04: Measure torque while mixing at different speeds. Document and compare with established limits.
  • Test Case OQ-05: Retrieve PLC logs post-testing. Ensure all entries are present and accurately reflect the operational parameters.

Deviations: Any deviations from the acceptance criteria must be documented, investigated, and resolved prior to final approval of the OQ results.

Approvals:

Prepared By: ______________________ Date: ____________

Approved By: ______________________ Date: ____________