Ophthalmic Sterile Filtration Skid (0.22 µm) – Traceability Matrix (URS ↔ Tests)

URS ID URS Statement Risk (H/M/L) DQ Test Ref IQ Test Ref OQ Test Ref PQ Test Ref Evidence/Record Result
URS-001 Confirm the skid meets design specifications for sterile filtration. M DQ-Ref-001 IQ-Ref-001 OQ-Ref-001 PQ-Ref-001 Design Specification Document
URS-002 Verify the integrity of the filtration system under flow conditions. H DQ-Ref-002 IQ-Ref-002 OQ-Ref-002 PQ-Ref-002 Integrity Test Results
URS-003 Ensure the integration audit trail is functioning correctly. M DQ-Ref-003 IQ-Ref-003 OQ-Ref-003 PQ-Ref-003 Audit Trail Verification Report
URS-004 Assess the flow rate during operation to ensure compliance. L DQ-Ref-004 IQ-Ref-004 OQ-Ref-004 PQ-Ref-004 Flow Rate Test Results
See also  Air Shower – Qualification Execution Checklist