Standard Operating Procedure for Equipment Validation of Dynamic HEPA Pass Box

Purpose: This SOP outlines the validation process for the Dynamic HEPA Pass Box used for material transfer within the facility, ensuring compliance with regulatory requirements and operational efficiency.

Scope: This procedure applies to the validation of the Dynamic HEPA Pass Box utilized in the Solid Dosage Form (OSD) manufacturing area.

Definitions:

  • Pass Box: A device used to transfer materials between controlled environments while minimizing contamination.
  • HEPA: High-Efficiency Particulate Air filter, used to maintain air quality.
  • Validation: The process of establishing documented evidence that a system meets its intended use.

Roles:

  • Validation Team: Responsible for executing the validation process.
  • Quality Assurance: Ensures compliance with regulatory standards and reviews validation documentation.
  • Maintenance Personnel: Conducts calibration and preventive maintenance as per schedule.

Lifecycle Procedure:

  1. Design Qualification (DQ): Assess user requirements and ensure equipment specifications meet operational needs.
  2. Installation Qualification (IQ): Verify the installation of the Pass Box according to manufacturer specifications.
  3. Operational Qualification (OQ): Test the Pass Box’s operational parameters to ensure it functions as intended.
  4. Performance Qualification (PQ): Confirm the Pass Box performs effectively under actual operating conditions.

GDP Controls: Good Documentation Practices (GDP) must be followed throughout the validation process, ensuring all records are accurate, complete, and traceable.

Acceptance Criteria Governance: Acceptance criteria for the validation of the Pass Box will adhere to URS ISO 14644 Annex 11 guidelines, focusing on air cleanliness and particulate matter control.

See also  Bin Dryer (IBC Dryer) – Traceability Matrix (URS ↔ Tests)

Calibration/PM Governance: Calibration and preventive maintenance must be performed annually, with records maintained in accordance with standard operating procedures.

Change Control Triggers: Any modifications to the Pass Box or its operating procedures must initiate a change control process to assess potential impacts on validation status.

Revalidation Triggers and Periodic Review: Revalidation will occur every 12 months, or sooner if changes are made to the equipment or processes that could affect its performance.

Records/Attachments List:

  • Validation Protocols
  • Validation Reports
  • Calibration Certificates
  • Maintenance Logs
  • Change Control Documentation