Patch Coating Machine (Knife-over-roll / Slot Die) – IQ Protocol

Document ID: IQ-TDS-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Installation Qualification Protocol for Patch Coating Machine

Objective: To ensure that the Patch Coating Machine is installed correctly and functions according to specifications for the coating of drug adhesive layers onto backing films.

Scope: This protocol applies to the Installation Qualification of the Patch Coating Machine used in the production of transdermal patches.

Responsibilities:

  • Validation Team: Prepare and execute the IQ protocol.
  • Production Team: Provide access to the equipment and assist in the execution of tests.
  • Quality Assurance: Review and approve the IQ protocol and results.

Prerequisites:

  • Completion of equipment installation.
  • Training of personnel on equipment operation.
  • Availability of required documentation (URS, specifications).

Equipment Description:

The Patch Coating Machine (Knife-over-roll / Slot Die) is designed for the application of drug adhesive layers onto backing films with critical parameters including coating thickness, speed, temperature, tension, and PLC logs.

Test ID Procedure Acceptance Criteria Evidence
IQ-01 Verify equipment installation against manufacturer specifications. All components installed as per specifications. Installation checklist signed off.
IQ-02 Check calibration of critical parameters (thickness, speed, temp, tension). Parameters within specified limits. Calibration certificates.
IQ-03 Review PLC logs for accuracy and completeness. Logs show no discrepancies. PLC log printouts.

Detailed Test Cases:

  • Test Case ID: IQ-01
    • Objective: Confirm proper installation.
    • Procedure: Inspect all physical components.
    • Acceptance: All components installed correctly.
    • Evidence: Installation checklist.
  • Test Case ID: IQ-02
    • Objective: Validate calibration.
    • Procedure: Measure coating thickness, speed, temperature, and tension.
    • Acceptance: All readings within specified limits.
    • Evidence: Calibration certificates.
  • Test Case ID: IQ-03
    • Objective: Ensure PLC logs are accurate.
    • Procedure: Review PLC logs for discrepancies.
    • Acceptance: No discrepancies found.
    • Evidence: PLC log printouts.
See also  Inline Sifter (Transfer Line) – DQ Protocol

Deviations: Any deviations from the acceptance criteria must be documented and addressed as per the change control procedure.

Approvals:

  • Validation Team Lead: ___________________ Date: __________
  • Production Manager: ___________________ Date: __________
  • Quality Assurance: ___________________ Date: __________

Data Integrity Checks:

  • Ensure all PLC logs are securely stored and backed up.
  • Conduct periodic reviews of calibration data to maintain compliance.
  • Implement access controls to prevent unauthorized changes to critical parameters.