Pin Mill – OQ Protocol

Operational Qualification Protocol for Pin Mill in Solid Dosage Form

Document Number: OQ-PM-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Prepared By: [Insert Name]

Approved By: [Insert Name]

Objective

The objective of this Operational Qualification (OQ) protocol is to verify that the Pin Mill operates according to defined specifications and meets the acceptance criteria as outlined in the User Requirement Specification (URS).

Scope

This protocol applies to the Pin Mill located in the Production/Milling area, utilized for fine milling in the manufacturing of solid dosage forms. The focus is on direct product impact with major criticality.

Responsibilities

It is the responsibility of the Validation Team to execute this OQ protocol, ensuring compliance with regulatory requirements and internal standards.

Prerequisites

All personnel involved in the execution of this protocol must be trained in Good Manufacturing Practices (GMP) and familiar with the operation of the Pin Mill.

Equipment Description

The Pin Mill is a high-speed milling device designed to produce fine particle sizes in solid dosage forms. Key features include adjustable disc speed, temperature control, and a robust design for continuous operation.

Test Plan

Test ID Procedure Acceptance Evidence
OQ-PM-01 Verify disc speed output Disc speed within specified range Calibration report
OQ-PM-02 Measure particle size distribution (PSD) PSD meets URS specifications Test results
OQ-PM-03 Monitor temperature during operation Temperature remains within specified limits Temperature log

Detailed Test Cases

Test Case 1: Verify Disc Speed Output

Procedure: Set the Pin Mill to the desired operating speed and record the output speed using a calibrated tachometer. Compare against the specified range in the URS.

See also  Vibro Sifter – Validation Summary Report (VSR) Template

Acceptance Criteria: Disc speed must be within the specified range as per URS.

Evidence: Calibration report and recorded measurements.

Test Case 2: Measure Particle Size Distribution (PSD)

Procedure: Collect samples during milling and analyze using a laser diffraction particle size analyzer.

Acceptance Criteria: PSD must meet the specifications outlined in the URS.

Evidence: Test results report from the particle size analyzer.

Test Case 3: Monitor Temperature During Operation

Procedure: Continuously monitor the temperature of the milling chamber during operation and log data.

Acceptance Criteria: Temperature must remain within the specified limits as per URS.

Evidence: Temperature log and compliance report.

Deviations

Any deviations from the protocol must be documented and justified. A deviation report will be generated for review and approval.

Approvals

All test results and deviations must be reviewed and approved by the Validation Team Lead and Quality Assurance.