Pneumatic Conveying (Dilute Phase) – IQ Protocol

Installation Qualification Protocol for Pneumatic Conveying System

Document Number: IQ-001

Version: 1.0

Date: 2023-10-01

Prepared By: [Your Name]

Approved By: [Approver’s Name]

Objective

The objective of this Installation Qualification (IQ) Protocol is to verify that the Pneumatic Conveying System is installed according to the manufacturer’s specifications and operational requirements, ensuring compliance with URS Annex11 standards.

Scope

This protocol applies to the Pneumatic Conveying System used in the Production/Material Transfer area for Solid Dosage Form (OSD) applications. The system is utilized for conveying materials via an air stream, directly impacting product quality.

Responsibilities

  • Validation Team: Responsible for executing the IQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the protocol and results.
  • Engineering: Responsible for the installation and maintenance of the equipment.

Prerequisites

  • Completion of equipment installation by Engineering.
  • Availability of all relevant documentation (URS, design specifications, etc.).
  • Training of personnel on the operation of the Pneumatic Conveying System.

Equipment Description

The Pneumatic Conveying System (Dilute Phase) is designed for the efficient transfer of materials through an air stream. Key features include:

  • Airflow velocity control
  • Pickup and receiver performance monitoring
  • PLC integration for automated operations

Test Plan

Test ID Procedure Acceptance Evidence
IQ-01 Verify installation against manufacturer’s specifications All components installed as per specifications Installation checklist
IQ-02 Check airflow velocity at pickup and receiver Airflow within specified range Measurement logs
IQ-03 Test PLC functionality PLC operates as intended PLC test report
See also  Vacuum Transfer System (Mobile) – IQ Protocol

Detailed Test Cases

Test Case IQ-01

Procedure: Inspect all components of the Pneumatic Conveying System to ensure they are installed according to the manufacturer’s specifications.

Acceptance Criteria: All components must be installed as per specifications outlined in the installation manual.

Evidence: Complete the installation checklist and attach photographs of the installation.

Test Case IQ-02

Procedure: Measure the airflow velocity at both the pickup and receiver points using calibrated equipment.

Acceptance Criteria: Airflow must be within the specified range of [insert range].

Evidence: Record measurements in the measurement logs.

Test Case IQ-03

Procedure: Perform a functionality test of the PLC, ensuring all controls respond as expected.

Acceptance Criteria: PLC must operate without errors and control the system as intended.

Evidence: Document PLC test results and any anomalies encountered.

Deviations

Any deviations from the acceptance criteria must be documented and investigated. A CAPA (Corrective and Preventive Action) plan should be initiated for any significant deviations affecting system performance.

Approvals

Prepared By: [Your Name] – [Your Position]

Approved By: [Approver’s Name] – [Approver’s Position]

“`