PW Distribution Loop – DQ Protocol

Document Control

Document ID: DQ-PWDL-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approved By: [Insert Name]

Design Qualification Protocol for PW Distribution Loop

Objective: To ensure that the PW Distribution Loop is designed to meet the necessary requirements for the distribution of purified water in compliance with regulatory standards.

Scope: This protocol applies to the Design Qualification of the PW Distribution Loop used in the Utilities area for the distribution of purified water, impacting product quality directly.

Responsibilities:

  • Validation Team: Responsible for executing the DQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the DQ protocol and results.
  • Engineering: Responsible for providing necessary equipment specifications and design documentation.

Prerequisites:

  • Completion of User Requirements Specification (URS).
  • Availability of design documentation for the PW Distribution Loop.
  • Approval from Quality Assurance for the DQ protocol.

Equipment Description: The PW Distribution Loop is designed to distribute purified water throughout the facility, ensuring compliance with regulatory standards for microbial control and temperature flow.

Test ID Procedure Acceptance Criteria Evidence
DQ-001 Verify design specifications against URS. All specifications must match URS Annex11 Annex15. Design Specification Document.
DQ-002 Conduct temperature flow validation. Temperature must remain within specified limits. Temperature Log.
DQ-003 Perform microbial control assessment. No microbial contamination detected. Microbial Test Results.
DQ-004 Review audit trail functionality. Audit trail must capture all critical parameters. Audit Trail Report.
See also  Leak Test Machine (Container Closure) – Traceability Matrix (URS ↔ Tests)

Detailed Test Cases

Test Case 1: Verify design specifications against URS.

  • Review the design documentation.
  • Ensure all specifications align with URS Annex11 Annex15.

Test Case 2: Conduct temperature flow validation.

  • Monitor the temperature during operation.
  • Document temperature readings over a specified period.

Test Case 3: Perform microbial control assessment.

  • Collect samples from various points in the distribution loop.
  • Send samples for microbial testing.

Test Case 4: Review audit trail functionality.

  • Access the system’s audit trail.
  • Verify that all critical parameters are logged appropriately.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on product quality. A corrective action plan must be developed and implemented.

Approvals

This DQ protocol must be reviewed and approved by the Quality Assurance team before execution.