Shaking Incubator – OQ Protocol

Document Control:

Document Number: OQ-001

Version: 1.0

Effective Date: [Insert Date]

Review Date: [Insert Date]

Operational Qualification Protocol for Shaking Incubator in Cell Culture Growth

Objective: To validate the operational performance of the Shaking Incubator used for cell culture growth in the production area, ensuring compliance with URS Annex11.

Scope: This protocol applies to the Shaking Incubator utilized in upstream processing for biologics production. It covers the validation of critical parameters including temperature, RPM, and uniformity.

Responsibilities:

  • Validation Team: Execute the protocol and document results.
  • Quality Assurance: Review and approve the protocol and final report.
  • Production Team: Provide access to the equipment and assist in the execution of the tests.

Prerequisites:

  • Shaking Incubator installed and operational.
  • Standard Operating Procedures (SOPs) for equipment use in place.
  • Training completed for personnel involved in the qualification.

Equipment Description: The Shaking Incubator is designed for optimal cell culture growth through controlled shaking and temperature settings. It is equipped with PLC logs for monitoring operational parameters.

Test ID Procedure Acceptance Criteria Evidence
OQ-01 Verify temperature uniformity across the chamber. ±2°C from set point. Temperature mapping report.
OQ-02 Check RPM uniformity during operation. ±10% of set RPM. RPM log data.
OQ-03 Review PLC logs for operational consistency. No critical alarms or failures. PLC log report.

Detailed Test Cases:

  • Test Case OQ-01: Conduct temperature mapping using calibrated thermocouples. Record temperatures at various points within the incubator to assess uniformity.
  • Test Case OQ-02: Use a calibrated tachometer to measure RPM at multiple points. Ensure readings fall within acceptance criteria.
  • Test Case OQ-03: Extract PLC logs for the past 30 days. Review for any deviations or alarms that may indicate operational issues.
See also  Auto Coating Pan (Perforated Pan Coater) – PQ Protocol

Deviations: Any deviations from the acceptance criteria must be documented and assessed for impact on product quality. A corrective action plan should be developed as necessary.

Approvals:

  • Validation Team Lead: ____________________ Date: ___________
  • Quality Assurance: ____________________ Date: ___________

Data Integrity Checks:

  • Ensure all data entered into the system is timestamped and attributed to the responsible individual.
  • Perform periodic audits of PLC logs to verify data accuracy and completeness.
  • Implement backup procedures for critical data to prevent loss.