Objective

The objective of this Design Qualification (DQ) protocol is to establish documented evidence that the Sigma Mixer / Kneader is designed and installed in compliance with the User Requirements Specification (URS) for high-viscosity mass mixing in the Solid Dosage Form production area.

Scope

This protocol applies to the Sigma Mixer / Kneader utilized in the Production/Granulation area for the manufacturing of solid dosage forms. The DQ will cover the equipment’s design specifications, installation, and operational performance.

Responsibilities

  • Validation Team: Responsible for the execution and documentation of the DQ protocol.
  • Quality Assurance: Responsible for reviewing and approving the DQ protocol and reports.
  • Engineering: Responsible for providing technical specifications and installation support.

Prerequisites

  • Completion of User Requirements Specification (URS).
  • Installation of the Sigma Mixer / Kneader as per manufacturer’s guidelines.
  • Availability of operational manuals and training for personnel.

Equipment Description

The Sigma Mixer / Kneader is a high-viscosity mass mixing equipment designed for the production of solid dosage forms. It features adjustable blade speed, temperature control, and vacuum capabilities to ensure optimal mixing conditions.

Test Plan

Test ID Procedure Acceptance Evidence
T1 Verify blade speed settings. Blade speed within specified range. Calibration report.
T2 Check temperature control functionality. Temperature maintained within specified limits. Temperature log.
T3 Assess vacuum operation. Vacuum levels meet specifications. Vacuum gauge readings.
See also  Magnetic Separator (Inline) – DQ Protocol

Detailed Test Cases

Test Case 1: Blade Speed Verification

Procedure: Set the mixer to the specified blade speed and record the actual speed.

Acceptance Criteria: The actual blade speed must be within ±5% of the specified speed.

Evidence: Calibration report and speed measurement log.

Test Case 2: Temperature Control Assessment

Procedure: Run the mixer and monitor the temperature for stability over a 30-minute period.

Acceptance Criteria: The temperature must remain within ±2°C of the target temperature.

Evidence: Temperature control log.

Test Case 3: Vacuum Operation Evaluation

Procedure: Engage the vacuum and monitor the levels during operation.

Acceptance Criteria: Vacuum levels must reach and maintain the specified threshold.

Evidence: Vacuum gauge readings documented during operation.

Deviations

Any deviations from the acceptance criteria must be documented and assessed for impact on the validation process. A corrective action plan must be developed if critical parameters are not met.