Purpose

The purpose of this SOP is to provide a structured approach for the validation of the Slitting Machine used in the production of Transdermal Patches, ensuring that it operates consistently and produces quality products.

Scope

This procedure applies to the Slitting Machine utilized in the production area for cutting coated rolls into strips for Transdermal Patches. It encompasses all validation phases including DQ, IQ, OQ, and PQ.

Definitions

  • DQ: Design Qualification
  • IQ: Installation Qualification
  • OQ: Operational Qualification
  • PQ: Performance Qualification
  • CSV: Computerized System Validation
  • URS: User Requirements Specification

Roles

  • Validation Team: Responsible for the execution of validation activities.
  • Quality Assurance: Ensures compliance with regulatory standards and documentation.
  • Production Personnel: Operate the Slitting Machine and provide input during validation.

Lifecycle Procedure

  1. Conduct Design Qualification (DQ) to establish user requirements.
  2. Perform Installation Qualification (IQ) to verify equipment installation.
  3. Execute Operational Qualification (OQ) to assess operational parameters.
  4. Complete Performance Qualification (PQ) to confirm equipment performance.

Good Documentation Practices (GDP) Controls

All validation documents must be completed in accordance with Good Documentation Practices (GDP), ensuring accuracy, legibility, and traceability.

Acceptance Criteria Governance

Acceptance criteria will align with the User Requirements Specification (URS) and Annex 11 guidelines, ensuring that all parameters meet predefined standards.

See also  Bin/IBC Washer – Deviation Impact Assessment

Calibration and Preventive Maintenance Governance

Calibration and preventive maintenance of the Slitting Machine must be conducted according to the established schedule to ensure optimal performance and compliance.

Change Control Triggers

Any changes to the Slitting Machine, including software updates, hardware modifications, or process changes, must trigger a change control process to assess impact on validation status.

Revalidation Triggers and Periodic Review

Revalidation of the Slitting Machine is required every 12 months or whenever significant changes occur that may affect the validated state.

Records and Attachments List

  • Validation Protocols and Reports
  • Calibration Certificates
  • Preventive Maintenance Records
  • Change Control Documentation
  • Training Records