Solvent Storage Tank (SS / GL) – OQ Protocol

Document Control:

Document ID: OQ-SS-001

Version: 1.0

Effective Date: [Insert Date]

Reviewed By: [Insert Name]

Approval Date: [Insert Date]

Operational Qualification Protocol for Solvent Storage Tank in API Manufacturing

Objective: To establish the operational qualification (OQ) of the Solvent Storage Tank to ensure it meets the required specifications and performance criteria for storing solvents in the production area.

Scope: This protocol applies to the Solvent Storage Tank used for solvent storage in API manufacturing processes, focusing on the verification of critical parameters.

Responsibilities:

  • Validation Team: Responsible for executing the OQ protocol and documenting results.
  • Quality Assurance: Responsible for reviewing and approving the OQ protocol and results.
  • Production Personnel: Responsible for providing access and support during testing.

Prerequisites:

  • Installation Qualification (IQ) must be completed and approved.
  • All necessary documentation and equipment must be available and functioning.

Equipment Description:

The Solvent Storage Tank (SS / GL) is designed to store solvents used in the chemical synthesis and purification processes within the production area. The tank is equipped with level, temperature, and pressure sensors, and is controlled via a PLC with an audit trail log feature.

Test ID Procedure Acceptance Criteria Evidence
OQ-01 Verify level sensor calibration Calibration within specified limits Calibration certificate
OQ-02 Verify temperature sensor accuracy Temperature within specified limits Temperature log
OQ-03 Verify pressure sensor functionality Pressure readings within specified limits Pressure log
OQ-04 Check PLC audit trail logs Complete and accurate logs maintained Audit trail report
See also  Bin Lifter / IBC Lifter – Traceability Matrix (URS ↔ Tests)

Detailed Test Cases:

  1. Test Case OQ-01: Verify the calibration of the level sensor. Document the calibration procedure and results.
  2. Test Case OQ-02: Measure the temperature using a calibrated thermometer and compare it with the temperature sensor reading.
  3. Test Case OQ-03: Apply known pressure to the tank and verify the pressure sensor readings against the applied pressure.
  4. Test Case OQ-04: Review the PLC audit trail logs for completeness and accuracy over a defined period.

Deviations:

Any deviations from the acceptance criteria must be documented and investigated. Corrective actions should be implemented as necessary.

Approvals:

All results must be reviewed and approved by the Quality Assurance department before final acceptance of the OQ protocol.