Static Incubator – PQ Protocol

Document ID: PQ-SI-001

Version: 1.0

Effective Date: YYYY-MM-DD

Prepared by: [Your Name]

Approved by: [Approver’s Name]

Performance Qualification Protocol for Static Incubator in Biologics Upstream Processing

Objective: To ensure that the Static Incubator operates within specified parameters to support cell incubation in the production area, meeting the defined acceptance criteria.

Scope: This protocol applies to the Performance Qualification of the Static Incubator used in the Production/Cell Culture area for biologics upstream processing.

Responsibilities:

  • Validation Team: Prepare, execute, and document the PQ protocol.
  • Quality Assurance: Review and approve the PQ protocol and results.
  • Production Personnel: Ensure proper operation and maintenance of the Static Incubator.

Prerequisites:

  • Installation Qualification (IQ) must be completed and approved.
  • Operational Qualification (OQ) must be completed and approved.
  • Personnel trained on the operation of the Static Incubator.

Equipment Description:

The Static Incubator is designed for cell incubation, providing controlled temperature conditions critical for cell culture processes. The incubator features temperature uniformity monitoring through PLC logs.

Test ID Procedure Acceptance Criteria Evidence
PQ-SI-01 Verify temperature uniformity using PLC logs. Temperature uniformity within ±2°C of setpoint. PLC log reports.
PQ-SI-02 Perform a 24-hour stability test. Temperature remains stable within ±2°C. Stability test report.

Detailed Test Cases:

Test Case PQ-SI-01:

  • Access the PLC logs for the Static Incubator.
  • Record the temperature readings at specified intervals.
  • Analyze data for temperature uniformity.
See also  Dust Extraction Unit (LEV for dispensing) – PQ Protocol

Test Case PQ-SI-02:

  • Set the incubator to the desired temperature.
  • Monitor temperature continuously for 24 hours.
  • Document any deviations and ensure corrective actions are taken.

Deviations:

Any deviations from the acceptance criteria must be documented and investigated. Corrective actions must be implemented and verified.

Approvals:

All results must be reviewed and approved by the Quality Assurance department before final validation of the Static Incubator.

Data Integrity Checks:

  • Ensure PLC logs are automatically recorded and time-stamped.
  • Regular audits of log files to confirm data accuracy and completeness.
  • Backup of log data at defined intervals to prevent data loss.